The Project Board wants to provide ad-hoc direction to the Project Manager regarding a critical issue. Which process should the Project Board use?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
Directing a Project includes the activity 'Giving ad hoc direction' to allow the Project Board to provide guidance or decisions outside of formal stage boundaries.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing Product Delivery
Why it's wrong here
MP is the Team Manager process; the Board does not perform MP.
- ✗
Initiating a Project
Why it's wrong here
IP is for establishing the project foundation; ad-hoc direction can occur at any time via DP.
- ✗
Controlling a Stage
Why it's wrong here
CS is the PM's process; the Board does not perform CS.
- ✓
Directing a Project
Why this is correct
Correct. Giving ad hoc direction is a key activity of DP.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.