Courseiva
PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

The Project Board is reviewing an Exception Plan and decides to approve it. Which process is the Project Board executing?

⚠ Common exam trap

The trap is confusing the process where the Exception Plan is created (Managing a Stage Boundary) with the process where it is approved (Directing a Project); candidates often pick Managing a Stage Boundary because they associate Exception Plans with that process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Directing a Project

The Project Board is responsible for the Directing a Project process, which includes approving Exception Plans. When the Project Board approves an Exception Plan, they are performing a decision-making activity within the Directing a Project process. The Exception Plan is created during Managing a Stage Boundary, but the approval itself is a Directing activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Controlling a Stage

    Why it's wrong here

    Controlling a Stage is where the Project Manager manages day-to-day work, and the Board's approval of an Exception Plan is a Board decision within the directing layer, not this process. Controlling a Stage suits the Project Manager's routine progress monitoring against stage tolerances.

  • ✗

    Closing a Project

    Why it's wrong here

    Approving an Exception Plan occurs within Directing a Project, where the Project Board authorises continued work after a Stage Boundary or exception. Closing a Project handles final product acceptance, handover and project closure, so it cannot approve an Exception Plan. It would be correct when confirming the project has delivered everything and can be disbanded.

  • ✓

    Directing a Project

    Why this is correct

    Approving an Exception Plan is a Project Board decision within Directing a Project, specifically the "Authorise an Exception Plan" activity. This satisfies the stem's constraint that the Board is executing a directing-level process, since Exception Plans escalate beyond Project Manager tolerances and require Board authority to approve.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary produces the Exception Plan, but the Board approves it during Directing a Project.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. The Project Board is considering whether to approve an Exception Plan. Which process should they use to make this decision?

hard
  • A.Managing a Stage Boundary
  • ✓ B.Directing a Project
  • C.Controlling a Stage
  • D.Closing a Project

Why B: The Project Board is responsible for making key decisions and exercising overall control over the project. When an Exception Plan is submitted, it is the Project Board's role to review and approve or reject it, which is a core activity of the 'Directing a Project' process. This process covers all high-level decision-making, including authorizing deviations from the plan.

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.