Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

The Project Board is reviewing an Exception Plan and decides to approve it. Which process is the Project Board executing?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

Approving an Exception Plan is a key decision made by the Project Board during Directing a Project. The Project Board authorizes exception plans, stage plans, and closure. Controlling a Stage is for the PM. Managing a Stage Boundary produces the Exception Plan but the Board approves it. Closing a Project is for project closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Controlling a Stage

    Why it's wrong here

    Controlling a Stage is the PM's process for day-to-day management.

  • Closing a Project

    Why it's wrong here

    Closing a Project involves producing the End Project Report, not approving exception plans.

  • Directing a Project

    Why this is correct

    The Project Board authorizes exception plans during Directing a Project.

  • Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary produces the Exception Plan, but the Board approves it during Directing a Project.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. The Project Board is considering whether to approve an Exception Plan. Which process should they use to make this decision?

hard
  • A.Managing a Stage Boundary
  • B.Directing a Project
  • C.Controlling a Stage
  • D.Closing a Project

Why B: The Project Board is responsible for making key decisions and exercising overall control over the project. When an Exception Plan is submitted, it is the Project Board's role to review and approve or reject it, which is a core activity of the 'Directing a Project' process. This process covers all high-level decision-making, including authorizing deviations from the plan.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.