Starting Up a Project Outputs: Project Brief, Daily Log & Initiation Stage Plan
Which TWO of the following are outputs of the Starting Up a Project process?
⚠ Common exam trap
PRINCE2F often tests which process owns which product — candidates confuse Starting up a Project with Initiating a Project and incorrectly assign the Benefits Management Approach or PID to the earlier process.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Brief
Option A (Project Brief) is correct because Starting Up a Project (SU) creates the Project Brief as its primary output, capturing the project's outline business case, scope, objectives, and tolerances to feed into Initiating a Project. Option D (Daily Log) is correct because SU also establishes the Daily Log, which the Project Manager uses to record informal issues, actions, and notes throughout the project. Option B (Benefits Management Approach) is not correct because it is produced during Initiating a Project (IP), not SU. Option C (Project Initiation Documentation) is not correct because the PID is assembled in the Initiating a Project process. Option E (End Stage Report) is not correct because it is created in the Managing a Stage Boundary process at the end of a stage.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Brief
Why this is correct
The Project Brief is a required output of Starting Up a Project, produced from the Project Mandate and refined by the Project Manager. It satisfies the stem's constraint by being created before the Initiating a Project process begins, establishing the project's baseline definition for subsequent approval by the Project Board.
- ✗
Benefits Management Approach
Why it's wrong here
The Benefits Management Approach is created during the Initiating a Project process, alongside the Business Case and plans, not during Starting Up a Project. It is tempting because benefits thinking begins in the Project Brief, but the formal approach document is an Initiating a Project output, so it fails this stem.
- ✗
Project Initiation Documentation
Why it's wrong here
The Project Initiation Documentation is assembled during Initiating a Project, not Starting Up a Project. It is tempting because the Project Brief produced in Starting Up a Project feeds directly into the PID, but the PID itself is a distinct Initiating a Project output, so it does not satisfy this stem.
- ✓
Daily Log
Why this is correct
The Daily Log is created during Starting Up a Project as the repository for informal issues, actions and risks captured before the project formally begins. It satisfies the process's requirement to establish a working record that the Project Manager maintains throughout the project lifecycle.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is produced at the end of each stage in the Managing a Stage Boundary process, not during Starting Up a Project. It is tempting because both processes produce reports for the project board, but the End Stage Report reviews completed stage performance, whereas Starting Up a Project outputs the Project Brief and Daily Log.
Go deeper
Related to this question
About these practice questions
One of 1,186 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
You might also like
Similar PRINCE2F questions
- The Project Manager has produced an End Stage Report for the current stage. According to PRINCE2, what is the next step?
- During the Managing Product Delivery process, a Team Manager discovers that a product cannot meet its quality criteria w…
- Which TWO documents are produced during the Closing a Project process?
- In which process are the Project Board's key decisions made, such as authorizing initiation and authorizing stage plans?
- A project is approaching the end of its final stage. The Project Manager has confirmed that all products have been deliv…
Written and reviewed by Johnson Ajibi, MSc IT Security
Security Systems Architect · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.