Question 574 of 1,731
PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

Quick Answer

The answer is the Project Brief and the Daily Log. These are the two formal outputs of the Starting Up a Project process because this process focuses on evaluating the project’s viability before any detailed planning begins. The Project Brief provides the high-level justification, scope, and approach, while the Daily Log captures informal issues and actions during this startup phase. On the PRINCE2 Foundation exam, this question tests your ability to distinguish pre-initiation outputs from later documents like the Project Initiation Documentation or the Business Case, which are created during the Initiating a Project process. A common trap is confusing the Project Brief with the PID, but remember: the Brief is a starting point, not the final plan. For a memory tip, think “Start with a Brief and a Log” — the Brief gives the big picture, and the Log tracks the daily noise before formal controls kick in.

PRINCE2F PRINCE2 Processes Practice Question

This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are outputs of the Starting Up a Project process?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Daily Log

The Starting Up a Project process produces the Project Brief and the Daily Log as outputs. The Project Brief provides a high-level overview of the project's justification, scope, and approach, while the Daily Log is used to record informal issues, actions, and events during the startup phase. These are distinct from later-stage documents like the Project Initiation Documentation or End Project Report.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Initiation Documentation

    Why it's wrong here

    The PID is an output of Initiating a Project.

  • Daily Log

    Why this is correct

    Correct. The Daily Log is an output of SU.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Project Brief

    Why this is correct

    Correct. The Project Brief is an output of SU.

    Related concept

    Read the scenario before looking for a memorised answer.

  • End Project Report

    Why it's wrong here

    The End Project Report is an output of Closing a Project.

  • Benefits Management Approach

    Why it's wrong here

    The Benefits Management Approach is an output of Initiating a Project.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between the outputs of Starting Up a Project and Initiating a Project, trapping candidates who confuse the Project Brief (startup) with the Project Initiation Documentation (initiation).

Trap categories for this question

  • Command / output trap

    The PID is an output of Initiating a Project.

Detailed technical explanation

How to think about this question

The Starting Up a Project process is the first PRINCE2 process, executed before the project is formally authorized. Its outputs—the Project Brief and Daily Log—are essential for the Project Board to decide whether to proceed to initiation. The Daily Log is a simple, informal log that can later be migrated into the Issue Register or Risk Register if needed, but it remains a key tool for capturing ad-hoc items during startup.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Daily Log — The Starting Up a Project process produces the Project Brief and the Daily Log as outputs. The Project Brief provides a high-level overview of the project's justification, scope, and approach, while the Daily Log is used to record informal issues, actions, and events during the startup phase. These are distinct from later-stage documents like the Project Initiation Documentation or End Project Report.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

8 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Project Brief
  • B.Risk Register
  • C.Benefits Management Approach
  • D.Daily Log
  • E.Project Initiation Documentation (PID)

Why A: SU outputs include the Project Brief, initiation Stage Plan, Daily Log, and appointment of the Executive and PM. The PID and Risk Register are outputs from IP.

Variation 2. Which TWO of the following are outputs of the Starting Up a Project process?

easy
  • A.Initiation Stage Plan
  • B.Benefits Management Approach
  • C.Project Brief
  • D.End Project Report
  • E.Project Initiation Documentation

Why A: SU produces the Project Brief and the Stage Plan for the initiation stage. The Daily Log is also created but not a formal output. The PID is from IP.

Variation 3. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Project Initiation Documentation
  • B.End Stage Report
  • C.Project Brief
  • D.Benefits Management Approach
  • E.Initiation Stage Plan

Why C: SU produces the Project Brief, the initiation stage plan, and the Daily Log. The PID is an output of IP, and the Benefits Management Approach is an output of IP.

Variation 4. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Project Brief
  • B.Benefits Management Approach
  • C.Project Initiation Documentation
  • D.Daily Log
  • E.End Stage Report

Why A: Starting Up a Project produces the Project Brief, Initiation Stage Plan, and Daily Log. PID and Benefits Management Approach are from Initiating a Project. End Stage Report is from Managing a Stage Boundary.

Variation 5. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Project Initiation Documentation
  • B.Benefits Management Approach
  • C.Daily Log
  • D.End Stage Report
  • E.Project Brief

Why C: SU produces the Project Brief, Daily Log, and Initiation Stage Plan. PID is from IP.

Variation 6. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.End Project Report
  • B.Project Brief
  • C.Project Initiation Documentation
  • D.Initiation Stage Plan
  • E.Benefits Management Approach

Why B: SU produces the Project Brief, Stage Plan for initiation, and Daily Log. The PID is produced in IP, and the End Project Report is produced in CP.

Variation 7. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Benefits Management Approach
  • B.Project Brief
  • C.Project Initiation Documentation
  • D.Risk Management Approach
  • E.Daily Log

Why B: The Starting Up a Project process outputs the Project Brief, Daily Log, initiation Stage Plan, and appoints the Executive and Project Manager. The Risk Management Approach is developed later in Initiating a Project.

Variation 8. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Project Initiation Documentation
  • B.Project Brief
  • C.Daily Log
  • D.Benefits Management Approach
  • E.Stage Plan for the first delivery stage

Why B: SU produces the Project Brief, initiation Stage Plan, and Daily Log. The PID is produced in IP, and the Benefits Management Approach is also part of IP.

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.