Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Exhibit

Refer to the exhibit.

PRINCE2 Configuration Item Record
Item ID: CI-103
Product: User Authentication Module
Version: 2.1
Status: Under Development
Baseline: 2.0
Last Review: 2024-01-15
Owner: Project Support Office

Issue: The team reports that the latest version (2.1) has a critical defect. The status is 'Under Development' but the baseline is still 2.0. What process should the project manager follow?

Refer to the exhibit.

PRINCE2 Configuration Item Record Item ID: CI-103 Product: User Authentication Module Version: 2.1 Status: Under Development Baseline: 2.0 Last Review: 2024-01-15 Owner: Project Support Office

Issue: The team reports that the latest version (2.1) has a critical defect. The status is 'Under Development' but the baseline is still 2.0. What process should the project manager follow?

⚠ Common exam trap

PeopleCert often tests the distinction between managing issues within a stage (Controlling a Stage) versus escalating to the project board (Exception Report) or deferring to stage boundaries (Managing a Stage Boundary); the trap here is assuming that any defect automatically requires a baseline change or an exception report, when in fact the product is still under development and the defect can be handled as a normal issue within the current stage.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Log the defect as an issue and manage it through Controlling a Stage.

The defect in version 2.1 of the User Authentication Module is a new issue that must be formally logged and managed within the current stage. PRINCE2 requires that all issues (including defects) be captured in the Issue Register and handled through the Controlling a Stage process, which includes assessing the impact, deciding on corrective action, and updating the Configuration Item Record (CIR) accordingly. The baseline remains 2.0 because version 2.1 is still under development and has not been baselined, so the defect does not trigger a baseline change request.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Log the defect as an issue and manage it through Controlling a Stage.

    Why this is correct

    Issues are managed during Controlling a Stage.

  • Include the defect in the next Managing a Stage Boundary report.

    Why it's wrong here

    This is for stage boundaries, not for immediate issue handling.

  • Update the configuration item record and close the project.

    Why it's wrong here

    Closing the project is not appropriate for a defect.

  • Raise an exception report to the project board for a baseline change.

    Why it's wrong here

    The product is not baselined; it's under development.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.