Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

In the Directing a Project process, when does the project board authorize the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

At the end of the Initiating a Project process

The Board authorizes the project after reviewing the PID, which is produced in IP. This is the 'authorize the project' activity in DP.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • At the end of the Starting Up a Project process

    Why it's wrong here

    After SU, the Board decides whether to initiate, not authorize the full project.

  • At the end of the Initiating a Project process

    Why this is correct

    Correct. The Board authorizes the project (full funding) based on the PID.

  • At the end of the Managing a Stage Boundary process

    Why it's wrong here

    SB is about stage boundaries, not initial authorization.

  • At the end of the first stage

    Why it's wrong here

    The Board authorizes stages, but the project is authorized before the first stage begins.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.