PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

In the Directing a Project process, when does the project board authorize the project?

⚠ Common exam trap

The trap is that candidates might think the project is authorized at the end of Starting Up a Project or at the first stage boundary, but the correct point is after Initiating a Project, when the PID is approved.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

At the end of the Initiating a Project process

The project board authorizes the project at the end of the Initiating a Project process, when the Project Initiation Documentation (PID) is presented for approval. This is the 'Authorize the Project' activity in the Directing a Project process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    At the end of the Starting Up a Project process

    Why it's wrong here

    Starting Up a Project produces the project brief and daily log, ending when the project board reviews the brief and authorises the Initiation Stage, not the project itself. Authorising the project follows the Initiating a Project process, when the business case and plans exist.

  • ✓

    At the end of the Initiating a Project process

    Why this is correct

    The Project Board authorises the project at the end of Initiating a Project, once the Project Initiation Documentation and business case are complete. This satisfies the stem because authorisation follows the Project Board's review of the PID at the first End Stage Assessment, not during Starting Up a Project.

  • ✗

    At the end of the Managing a Stage Boundary process

    Why it's wrong here

    Managing a Stage Boundary prepares the next stage plan and exception reports for the board to approve the following stage. It occurs after the project is already authorised and underway, so it cannot be the point at which the board first authorises the project.

  • ✗

    At the end of the first stage

    Why it's wrong here

    The first stage is the Initiation Stage, which runs after the board has already authorised the project. Its end triggers the board's decision to authorise the next stage, so this timing sits downstream of project authorisation rather than being it.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.