In the Directing a Project process, when does the project board authorize the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
At the end of the Initiating a Project process
The Board authorizes the project after reviewing the PID, which is produced in IP. This is the 'authorize the project' activity in DP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
At the end of the Starting Up a Project process
Why it's wrong here
After SU, the Board decides whether to initiate, not authorize the full project.
- ✓
At the end of the Initiating a Project process
Why this is correct
Correct. The Board authorizes the project (full funding) based on the PID.
- ✗
At the end of the Managing a Stage Boundary process
Why it's wrong here
SB is about stage boundaries, not initial authorization.
- ✗
At the end of the first stage
Why it's wrong here
The Board authorizes stages, but the project is authorized before the first stage begins.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.