During the Controlling a Stage process, which report does the Project Manager send to the Project Board?

⚠ Common exam trap

In PRINCE2, candidates often confuse the Checkpoint Report (sent to the Project Manager by team managers) with the Highlight Report (sent to the Project Board by the Project Manager) due to their similar names and periodic nature. This distinction is critical in the Controlling a Stage process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Highlight Report

In the Controlling a Stage process, the Project Manager sends the Highlight Report to the Project Board at regular intervals to provide a summary of progress against the stage plan, including achievements, next steps, and any issues or risks. This report is the standard communication tool for keeping the board informed during a stage, as defined in PRINCE2.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Exception Report

    Why it's wrong here

    Exception Report is only used when tolerances are forecast to be exceeded.

  • Checkpoint Report

    Why it's wrong here

    Checkpoint Reports are from Team Manager to PM.

  • End Stage Report

    Why it's wrong here

    End Stage Report is produced in SB.

  • Highlight Report

    Why this is correct

    Highlight Report is sent to the Project Board.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In the Controlling a Stage process, which document does the Project Manager send to the Project Board to report progress?

medium
  • A.Checkpoint Report
  • B.End Stage Report
  • C.Exception Report
  • D.Highlight Report

Why D: The Highlight Report is the correct document because it is the formal mechanism by which the Project Manager provides the Project Board with a summary of progress, achievements, and next planned steps at regular intervals during the Controlling a Stage process. It is specifically designed to keep the Board informed without requiring their approval for day-to-day management.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.