Courseiva

PRINCE2F Business Case and Organizing Practice Question

During a project, the project manager identifies that a key supplier is consistently failing to meet quality standards. The project manager needs to escalate this issue to the project board. Who on the project board is accountable for the quality of the supplier's products and should be involved in resolving this issue?

⚠ Common exam trap

The trap here is assuming the Executive is responsible for all escalated issues, but in PRINCE2 the Senior Supplier is specifically accountable for supplier product quality.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Senior Supplier

The Senior Supplier is the project board role accountable for the quality of products delivered by suppliers. This role represents the supplier's interests and ensures that the supplier's resources are properly allocated and that products meet the required quality standards. When a supplier consistently fails to meet quality standards, the project manager should escalate the issue to the Senior Supplier, who can take appropriate action within the supplier organization.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Executive

    Why it's wrong here

    The Executive is ultimately accountable for the project's success, but the specific responsibility for supplier product quality lies with the Senior Supplier. The Executive focuses on the business justification and overall direction, not on the day-to-day quality of supplier deliverables.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager manages the project on a day-to-day basis and would address supplier performance issues, but the accountability for supplier product quality rests with the Senior Supplier on the project board. The Project Manager escalates to the board when issues cannot be resolved at the project level.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User is responsible for specifying benefits and ensuring that the project meets user needs, but not for supplier product quality. The Senior User focuses on the user perspective and benefits realization, not on the technical quality of supplier products.

  • ✓

    Senior Supplier

    Why this is correct

    The Senior Supplier is the project board role accountable for the quality of products delivered by the supplier. This role represents the supplier's interests and ensures that the supplier's resources are properly allocated and that products meet the required quality standards. Escalating supplier quality issues to the Senior Supplier is appropriate.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.