PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

An issue is raised that a product delivered by a supplier does not include a feature that was agreed in the product description. The Project Manager determines that the product is still usable without the feature. What type of issue is this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Off-specification

An Off-specification is something that should be provided but is not (or is provided but does not meet specifications). A Request for Change is a proposed change. A Problem/Concern is a general issue. Here, the feature is missing, so it's an Off-specification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Request for Change

    Why it's wrong here

    A request for change proposes altering a baseline, such as adding the missing feature back into the product description. Here the Project Manager accepts the product as delivered, so no change is requested. An RFC would be correct if the customer demanded the feature be reinstated.

  • ✓

    Off-specification

    Why this is correct

    The supplier delivered a product that fails to meet its agreed product description, yet remains usable. PRINCE2 classifies any such failure to meet specification as an off-specification issue, distinct from a change request or a general concern, so this correctly matches the stem's scenario.

  • ✗

    Problem/Concern

    Why it's wrong here

    A problem or concern covers any other issue needing Project Manager attention, but this scenario is specifically an off-specification: delivered work failing to meet an agreed product description. Because the product remains usable, the Project Manager records it as a concession rather than escalating it as a general concern.

  • ✗

    Risk

    Why it's wrong here

    A risk is an uncertain future event that may affect objectives, whereas this is a confirmed deviation already present in a delivered product. The missing feature has occurred, not merely threatened. Risk would be correct if the team anticipated the supplier might omit the feature before delivery.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.