A project manager is tailoring PRINCE2 for a small internal project. The project board wants to ensure that the 'Manage by Stages' principle is applied appropriately. Which TWO statements correctly describe how this principle is applied in PRINCE2? (Choose two.)

⚠ Common exam trap

The trap here is thinking that management stages must be equal in length or that technical stages are the same as management stages for control purposes.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

At least two management stages are required: one for initiation and one for delivery.

Manage by Stages means dividing the project into management stages, with a minimum of initiation and at least one delivery stage. Each management stage is authorized by the project board, which reviews the business case and approves the next stage plan. Stages may vary in length and are tailored to the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Technical stages are the same as management stages and are used for reporting progress.

    Why it's wrong here

    Technical stages are groups of work related to a specific technical specialty, such as design or build, and are not the same as management stages. Management stages are used for authorization and reporting; technical stages are internal to delivery and do not require board authorization.

  • ✗

    Management stages must always be of equal duration to ensure consistent reporting.

    Why it's wrong here

    Management stages can vary in length and number depending on the project's size, complexity, and risk. There is no requirement for equal duration. The number and length of stages are tailored to the project's needs and the level of control required.

  • ✓

    At least two management stages are required: one for initiation and one for delivery.

    Why this is correct

    PRINCE2 mandates a minimum of two management stages: an initiation stage and at least one delivery stage. This ensures that the project is properly initiated before delivery work begins, and that the board can authorize the delivery stage separately.

  • ✓

    The project is divided into management stages, each of which is authorized by the project board.

    Why this is correct

    Manage by Stages requires the project to be planned and controlled at management stage boundaries. Each management stage is authorized by the project board, which reviews progress and approves the next stage plan, ensuring continued viability and control.

  • ✗

    The project board delegates the authority to authorize each stage to the project manager.

    Why it's wrong here

    The project board retains the authority to authorize each management stage. It may delegate some project assurance or change authority, but the decision to proceed to the next stage remains with the board, except where the board explicitly delegates stage authorization to an executive or senior user.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.