PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A Project Manager is preparing the Project Initiation Documentation. In which process is this work done?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiating a Project

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, which establishes the solid foundation for the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why it's wrong here

    SU produces the Project Brief, not the PID.

  • Directing a Project

    Why it's wrong here

    DP is the Project Board process and does not produce the PID.

  • Managing Product Delivery

    Why it's wrong here

    MP is the Team Manager process for delivering work packages.

  • Initiating a Project

    Why this is correct

    Correct. The PID is created during the Initiating a Project process.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.