PRINCE2F Business Case and Organizing Practice Question

A project is in the Starting up a Project process. The Project Manager is drafting the Project Brief. Which role is responsible for providing the outline of the business case and confirming that the project is aligned with corporate strategy?

⚠ Common exam trap

The trap here is assuming that the Project Manager, who drafts the Project Brief, is also accountable for the business case content, when in PRINCE2 the Executive owns the business case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive is accountable for the business case and ensures that the project aligns with corporate strategy. During Starting up a Project, the Executive provides the outline business case, which is then documented in the Project Brief by the Project Manager. This outline is later expanded into the full Business Case during Initiating a Project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Assurance

    Why it's wrong here

    Project Assurance provides independent oversight and ensures that the project is being managed correctly. They do not provide the outline business case; they may review it, but the accountability for its content and strategic alignment rests with the Executive.

  • ✓

    Executive

    Why this is correct

    The Executive is accountable for the project and is responsible for providing the outline of the business case during Starting up a Project. They ensure that the project aligns with corporate strategy and that the business case is viable, which is crucial for obtaining authorization to initiate the project.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User is responsible for specifying the needs of the users and ensuring that the solution will deliver the expected benefits. While they contribute to the business case, they are not accountable for providing the outline business case or confirming strategic alignment; that is the Executive's role.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager is responsible for drafting the Project Brief, including the outline business case, but they do not own it. The Project Manager facilitates the process and ensures the information is gathered, but the accountability for strategic alignment lies with the Executive.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.