PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

A project is in the Initiating a Project process and the Project Manager is preparing the Project Plan. Which technique is recommended by PRINCE2 for creating the Project Plan?

⚠ Common exam trap

PRINCE2 Foundation often tests the distinction between product-based (PRINCE2) and activity-based (PMBOK) planning. Candidates may mistakenly choose Work Breakdown Structure (WBS) because it is a common planning tool in other frameworks, but PRINCE2 specifically uses Product-Based Planning with a Product Breakdown Structure (PBS).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Product-Based Planning

PRINCE2 recommends Product-Based Planning as the technique for creating the Project Plan. This approach focuses on defining the project's products (outputs) and their required quality criteria, then breaking them down into a Product Breakdown Structure (PBS) and mapping the sequence of activities needed to create them. It ensures the plan is driven by the deliverables rather than activities, aligning with PRINCE2's product focus.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Work Breakdown Structure

    Why it's wrong here

    PRINCE2 recommends product-based planning, whose first step is the product breakdown structure, not a Work Breakdown Structure. A WBS decomposes activities or deliverables for task assignment and is used in other methodologies; it does not identify the products, their descriptions and dependencies that PRINCE2's plan requires.

  • ✗

    Critical Path Analysis

    Why it's wrong here

    Critical Path Analysis sequences activities and calculates float once a schedule of work packages exists, so it cannot itself produce the Project Plan's product breakdown and estimates. PRINCE2 recommends it later, during activity sequencing and scheduling, not as the technique for building the plan.

  • ✗

    Earned Value Management

    Why it's wrong here

    Earned Value Management measures cost and schedule performance against a baseline during delivery, so it cannot construct the Project Plan. It is the correct technique for tracking progress and forecasting once the plan is baselined and work has started, not for defining products and estimates.

  • ✓

    Product-Based Planning

    Why this is correct

    Product-Based Planning derives the plan from the products to be delivered, defining each product's description, quality criteria and required activities. This satisfies PRINCE2's recommended technique for the Project Plan, ensuring activities trace to deliverables rather than being listed arbitrarily.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.