PRINCE2 Processes →hardMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

A project is in an early stage and the Project Manager discovers a new risk that could cause a delay. The risk is within the stage tolerance. What should the Project Manager do?

⚠ Common exam trap

PRINCE2F often tests whether candidates escalate every new risk to the Project Board, confusing the need to inform with the formal Exception Report trigger, which is only a forecast breach of tolerance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Update the risk register and manage the risk within the stage

In PRINCE2, the Project Manager is authorized to manage risks and issues within the stage tolerance defined in the Stage Plan. If the risk is within tolerance, the Project Manager should update the Risk Register, take appropriate management action, and continue managing the stage without escalating to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Stop the project and seek guidance

    Why it's wrong here

    Stopping the project is disproportionate; a risk inside stage tolerance is managed by the Project Manager within the stage, without escalation or premature closure. Stopping is tempting as a cautious response, and would be correct only if the risk threatened the business case beyond tolerances set by the board.

  • ✗

    Immediately raise an Exception Report to the Project Board

    Why it's wrong here

    An Exception Report is only required when a tolerance is forecast to be exceeded; this risk sits within stage tolerance, so board escalation is unwarranted. Raising one is tempting because escalation feels diligent, and would be correct once the risk breaches stage tolerance and the board must decide.

  • ✓

    Update the risk register and manage the risk within the stage

    Why this is correct

    Because the risk falls within stage tolerance, the Project Manager handles it at that level: recording it in the risk register, assessing and implementing a response, and monitoring it. Escalation to the Project Board is only required when tolerance would be exceeded.

  • ✗

    Revise the project plan and inform the board

    Why it's wrong here

    Revising the project plan and informing the board exceeds the Project Manager's delegated authority; within stage tolerance the risk is handled at stage level without board escalation. Plan revision is tempting because it feels proactive, and would be correct only once the risk breaches tolerance and an Exception Plan is required.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.