PRINCE2F Project Initiation and Stages Practice Question

A PRINCE2 project is in the Initiation Stage. The project manager is preparing the Project Initiation Documentation (PID). Which of the following is a responsibility of the project board during this stage?

⚠ Common exam trap

Candidates often confuse the project board's approval role with the project manager's creation role, leading to selecting an option that describes project manager responsibilities.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Approving the Project Initiation Documentation.

During the Initiation Stage, the project board's key responsibility is to approve the PID, which includes the Business Case, plans, and controls. This approval allows the project to proceed. The project board does not write the PID or its components; that is the project manager's role. The board provides direction and makes decisions at key points.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Approving the Project Initiation Documentation.

    Why this is correct

    The project board is responsible for approving the PID at the end of the Initiation Stage. This approval authorizes the project to proceed and confirms that the project is viable and aligned with strategic objectives. The project board reviews the PID to ensure it contains the necessary information to manage the project and that the Business Case is sound.

  • ✗

    Creating the project plan.

    Why it's wrong here

    Creating the project plan is a project manager responsibility. The project manager develops the plan during the Initiation Stage, often with input from the team. The project board may review and approve the plan as part of the PID, but they do not create it. This maintains the principle of defined roles and responsibilities.

  • ✗

    Writing the detailed Business Case.

    Why it's wrong here

    Writing the detailed Business Case is typically the responsibility of the project manager, often with input from the senior user and other stakeholders. The project board provides guidance and approves the Business Case, but does not write it. This ensures separation of duties and that the project manager owns the development of project documentation.

  • ✗

    Producing the End Project Report.

    Why it's wrong here

    The End Project Report is produced at the end of the project, not during Initiation. It is the project manager's responsibility to produce it. The project board receives and reviews it to make a decision about project closure. During Initiation, the project board's focus is on approving the PID, not on end-of-project reporting.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.