A PRINCE2 project is in the final stage. The project manager has completed all products and is now preparing for project closure. The Project Board has asked for assurance that the project has delivered its objectives. Which activity is part of the Closing a Project process?

⚠ Common exam trap

The trap here is thinking that Highlight Reports or work package authorizations continue into closure, but those are activities of Controlling a Stage, not Closing a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Preparing the End Project Report

Closing a Project includes preparing the End Project Report, which evaluates the project's performance and confirms whether the objectives in the Business Case have been met. This report, along with the Lessons Report, helps the Project Board decide whether to approve project closure, ensuring that the project is formally closed and benefits are reviewed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Updating the Project Initiation Documentation

    Why it's wrong here

    Updating the Project Initiation Documentation typically happens in Managing a Stage Boundary or when changes occur. In Closing a Project, the focus is on the End Project Report and confirming that all products have been delivered and accepted.

  • ✓

    Preparing the End Project Report

    Why this is correct

    Preparing the End Project Report is a key activity in Closing a Project. It summarizes the project's performance against the Business Case, including benefits realized and lessons learned. This report provides the Project Board with the necessary information to approve project closure.

  • ✗

    Authorizing the final work package

    Why it's wrong here

    Authorizing work packages occurs in Controlling a Stage. By the time the project is closing, all work packages should have been completed and accepted. The final work package authorization would have happened earlier, not during Closing a Project.

  • ✗

    Producing a Highlight Report for the final stage

    Why it's wrong here

    Highlight Reports are produced during Controlling a Stage to inform the Project Board of progress. They are not part of Closing a Project, which focuses on confirming delivery, reviewing benefits, and producing the End Project Report.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.