Courseiva
mediumMultiple ChoiceObjective-mapped

MB-920 Practice Question: A project manager notices that resource bookings…

A project manager notices that resource bookings in a project are not reflecting in the schedule. The project uses Dynamics 365 Project Operations with a hybrid resource management approach. What is the most likely cause?

⚠ Common exam trap

A common mix-up: candidates confuse 'Soft Book' mode with generic resources, assuming soft bookings are the cause of missing schedule visibility, when in fact generic resources are the root issue because they lack the identity required for schedule integration.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project uses generic resources that have not been replaced with named resources.

In Dynamics 365 Project Operations with a hybrid resource management approach, generic resources are placeholders that do not have actual availability or booking details. When generic resources are used without being replaced by named resources, their bookings do not reflect in the schedule because the system cannot map them to real resource calendars or capacity. This is the most likely cause of the issue described.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The resource bookings are set to 'Soft Book' mode.

    Why it's wrong here

    Soft bookings still show on the schedule.

  • The resource calendar has been modified after booking.

    Why it's wrong here

    Calendar changes affect availability but not the reflection of existing bookings on the schedule.

  • The project uses generic resources that have not been replaced with named resources.

    Why this is correct

    In hybrid resource management, generic resources must be replaced with named resources for bookings to reflect on the schedule.

  • The project status is not updated to 'In Progress'.

    Why it's wrong here

    Status updates do not prevent bookings from appearing on the schedule.

About these practice questions

One of 930 original MB-920 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.