Risk Response and MitigationmediumMultiple ChoiceObjective-mapped

CRISC Risk Response and Mitigation Practice Question

Exhibit

Risk ID | Inherent Risk | Controls | Residual Risk | Response
Risk-001 | High | Firewall, IDS | Medium | Transfer
Risk-002 | Medium | Encryption | Low | Accept
Risk-003 | Critical | None | Critical | Mitigate

Refer to the exhibit. Based on the risk register, which risk response is applied to the risk with the highest inherent risk?

⚠ Common exam trap

The trap here is that candidates see a high inherent risk and automatically assume the response must be 'Mitigate' with technical controls, but the question tests the ability to recognize that purchasing insurance is a classic transfer response, not a reduction of the risk itself.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Transfer

The risk with the highest inherent risk (Risk A, with a score of 25) involves a critical database server lacking encryption at rest. The risk response chosen is 'Transfer,' which is implemented by purchasing a cyber insurance policy that specifically covers data breach costs and regulatory fines. This shifts the financial impact of the risk to the insurer without altering the technical vulnerability or likelihood of the event.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Transfer

    Why this is correct

    Risk-001 uses Transfer.

  • Avoid

    Why it's wrong here

    No avoidance is shown.

  • Accept

    Why it's wrong here

    Risk-001's response is not Accept.

  • Mitigate

    Why it's wrong here

    Risk-003 uses Mitigate but has Critical inherent.

About these practice questions

Courseiva writes every CRISC question from scratch — 983 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.