Courseiva
Risk Response and MitigationmediumDrag & DropObjective-mapped

CRISC Risk Response and Mitigation Practice Question

Order the steps for implementing a risk treatment plan.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Select risk response, then develop risk treatment plan, then obtain approval, then implement the plan, then monitor and review.

Risk treatment starts with selecting response, planning, approval, implementation, and monitoring.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Select risk response, then develop risk treatment plan, then obtain approval, then implement the plan, then monitor and review.

    Why this is correct

    This is the correct order because risk treatment must start with selecting the appropriate response (e.g., mitigate, transfer, accept, avoid), then planning how to execute it, obtaining formal approval, implementing the controls, and finally monitoring their effectiveness to ensure the risk is managed.

  • Select risk response, then obtain approval, then develop risk treatment plan, then implement the plan, then monitor and review.

    Why it's wrong here

    This is incorrect because approval should come after the treatment plan is developed, not before. You cannot approve a plan that hasn't been created yet.

  • Develop risk treatment plan, then select risk response, then obtain approval, then implement the plan, then monitor and review.

    Why it's wrong here

    This is incorrect because you must first decide the risk response (what to do) before creating a detailed plan. Developing a plan without knowing the chosen response is illogical.

  • Select risk response, then develop risk treatment plan, then implement the plan, then obtain approval, then monitor and review.

    Why it's wrong here

    This is incorrect because implementation should occur only after the plan has been approved by management. Implementing before approval risks wasting resources on unapproved actions.

About these practice questions

This CRISC question is part of Courseiva's 983-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.