Correct answer & explanation
✓
Starting up a Project
Starting up a Project is the pre-project process that runs until the Project Board decides whether to authorize initiation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Initiating a Project
Why it's wrong here
Initiating a Project is the first stage of the actual project, not pre-project.
- ✗
Controlling a Stage
Why it's wrong here
Controlling a Stage occurs during delivery stages after initiation.
- ✗
Directing a Project
Why it's wrong here
Directing a Project runs throughout the entire project lifecycle, not just pre-project.
- ✓
Starting up a Project
Why this is correct
Starting up a Project is designed as a brief pre-project process.
About these practice questions
Courseiva writes every PRINCE2-PRACTITIONER question from scratch — 297 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.