PRINCE2-PRACTITIONER Processes Practice Question
During the Initiating a Project (IP) process, the Project Manager needs to establish the project's schedule and resource requirements. Where should these be compiled?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
In the Project Management Plan
The schedule and resource requirements form part of the Project Management Plan, which is compiled during IP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
In the Highlight Report
Why it's wrong here
Highlight Reports are periodic progress reports sent to the Project Board during execution.
- ✓
In the Project Management Plan
Why this is correct
The Project Management Plan contains the overall schedule, resource allocations, and stage plans.
- ✗
In the Project Brief
Why it's wrong here
The Project Brief is created in SU and is replaced by the PID/PMP upon initiation.
- ✗
In the End Project Report
Why it's wrong here
End Project Reports are created during Closing a Project.
About these practice questions
Courseiva writes every PRINCE2-PRACTITIONER question from scratch — 297 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.