During the Closing a Project (CP) process, who is responsible for preparing the End Project Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Project Manager
The Project Manager prepares the End Project Report during Closing a Project for submission to the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Assurance
Why it's wrong here
Project Assurance checks the report, but creating it is the Project Manager's responsibility.
- ✗
The Corporate/Programme management
Why it's wrong here
Corporate receives summary evaluations, but the End Project Report is a project management product created by the PM.
- ✓
The Project Manager
Why this is correct
The Project Manager drafts the End Project Report to evaluate project performance.
- ✗
The Executive
Why it's wrong here
The Executive reviews the report; the Project Manager prepares it.
About these practice questions
One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.