A project is in the Managing a Stage Boundary (SB) process. The Project Manager has identified that the next stage requires specialized external resources that were not accounted for in the outline Business Case. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the Business Case and present the revised costs and justification to the Project Board at the stage boundary.

In SB, if significant changes emerge that affect costs or viability, the Project Manager must update the Business Case and highlight the variances to the Project Board in the End Stage Report / stage boundary submission so the Board can make an informed decision.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Business Case and present the revised costs and justification to the Project Board at the stage boundary.

    Why this is correct

    Stage boundaries are the precise control point to review updated costs and business justification before proceeding.

  • Cancel the project immediately without preparing an End Stage Report.

    Why it's wrong here

    Cancellation requires formal Project Board evaluation based on an Exception Report or End Stage Report.

  • Reduce the quality criteria of all upcoming products to offset the cost of the external resources.

    Why it's wrong here

    Quality criteria cannot be arbitrarily lowered to cover budget overruns without board approval.

  • Procure the external resources immediately using project contingency funds without informing the board.

    Why it's wrong here

    Major unexpected external resource costs impacting the Business Case must be approved by the Project Board.

About these practice questions

Courseiva writes every PRINCE2-PRACTITIONER question from scratch — 297 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint

This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.