PRINCE2-PRACTITIONER Processes Practice Question
Which THREE of the following activities are performed during the Managing a Stage Boundary (SB) process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Updating the Business Case
Managing a Stage Boundary includes planning the next stage, updating the Business Case, and preparing an End Stage Report.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Updating the Business Case
Why this is correct
The Business Case is updated to reflect current costs and viability before the next stage.
- ✓
Planning the next stage
Why this is correct
Creating the next stage plan is a primary purpose of SB.
- ✓
Preparing the End Stage Report
Why this is correct
The End Stage Report summarizes the performance of the stage just ending.
- ✗
Executing specialist Work Packages
Why it's wrong here
Work packages are executed during delivery stages via MP and CS.
- ✗
Appointing the initial Project Manager
Why it's wrong here
The Project Manager is appointed during Starting up a Project.
About these practice questions
One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.