During the Closing a Project process, the Project Manager must prepare a Follow-on Action Recommendations log. Who is the primary audience responsible for acting upon these recommendations after the project is closed?
Follow-on Action Recommendations are addressed to corporate, programme management or operational management, since these bodies own the products after closure and can authorise any remaining work. This satisfies the stem's requirement by identifying the audience outside the project with authority to act on the recommendations.
Why this answer
The Follow-on Action Recommendations log captures outstanding actions, risks, and issues that cannot be resolved before the project closes and must be handed over to those who will own the products or benefits after closure. PRINCE2 specifies that these recommendations are directed to corporate, programme management, or operational management — the bodies that will continue to manage, operate, or realise benefits from the delivered products. The Project Board and Project Manager are closing out their responsibilities, so they are not the ongoing audience.
Exam trap
PRINCE2-Practitioner often tests the confusion between the Project Board (which authorises closure) and the post-project recipients of Follow-on Action Recommendations, tricking candidates into selecting the Board as the ongoing owner.
How to eliminate wrong answers
Option B is wrong because Team Managers are responsible for delivering products within the project and have no ongoing ownership after the project closes. Option C is wrong because the Project Manager's role ends with the project; they prepare the log but do not act on it post-closure. Option D is wrong because the Project Board authorises closure and disbands — it is not the body that inherits and acts on follow-on recommendations.