In a large infrastructure project, the Project Board includes a representative from the user community, a representative of senior supplier interests, and an Executive representing business interests. Which PRINCE2 principle is being implemented?
The Project Board's three stakeholder perspectives — business, user and supplier — map directly onto PRINCE2's defined roles and responsibilities principle, which requires each stakeholder interest to be represented in the project management team structure.
Why this answer
The scenario describes the three primary Project Board interests — Business (Executive), User, and Supplier — each formally represented with defined accountabilities. This is the direct embodiment of the 'Defined roles and responsibilities' principle, which requires that the project management team structure be established with clear roles, and that the three primary stakeholder interests be represented on the Board. The presence of all three interests is the textbook signal for this principle.
Exam trap
The trap here is confusing 'Defined roles and responsibilities' (who is on the team and what they are accountable for) with 'Tailor to suit the project' (adapting the method) — candidates see 'large infrastructure project' and wrongly reach for tailoring.
How to eliminate wrong answers
Option B is wrong because 'Tailor to suit the project' concerns adapting PRINCE2's processes, themes, and products to the project's size, risk, and environment — it is not about who sits on the Board. Option C is wrong because 'Manage by exception' is about delegating authority with defined tolerances so the Board only intervenes when thresholds are breached, not about the composition of the Board. Option D is wrong because 'Continued business justification' is about ensuring there is a valid Business Case throughout the project, not about stakeholder representation on the governance body.