You are managing a software development project using an Agile approach. The team consists of 8 developers and 2 testers. During the last three sprints, the team has consistently delivered about 70% of planned story points. The product owner is frustrated because key features are being delayed. The team reports that they are spending too much time fixing defects found during testing, and that the testers are a bottleneck. Upon reviewing the definition of done, you notice that unit tests are required but not always written, and integration tests are done only at the end of the sprint. What is the BEST course of action to address the root cause?