You are the PM for a highway construction project. A key vendor informs you that they cannot deliver the steel beams on time due to a factory fire. This risk was identified in the risk register with a mitigation plan to have a backup supplier. However, the backup supplier's price is 20% higher. Which TWO actions should you take?