PMP Process — Managing Technical Aspects • Set 21
PMP Process — Managing Technical Aspects Practice Test 21 — 15 questions with explanations. Free, no signup.
You are the project manager for a construction project. During excavation, the team discovers an undocumented underground utility line that was not shown on any plans. This could delay the project and increase costs. Which TWO actions should you take FIRST? (Choose two.)