PMP Process — Managing Technical Aspects • Set 1
PMP Process — Managing Technical Aspects Practice Test 1 — 15 questions with explanations. Free, no signup.
During a project's execution phase, a key stakeholder requests a change that would add a new feature. The project manager estimates the impact: 2 additional weeks to schedule and $15,000 to budget. The project currently has 0 schedule reserve and $5,000 contingency reserve. What should the project manager do first?