PMP People — Leading Projects • Set 6
PMP People — Leading Projects Practice Test 6 — 15 questions with explanations. Free, no signup.
You are the project manager for a construction project. A risk event that was identified in the risk register has just occurred: a key supplier is unable to deliver critical materials on time. The risk response plan includes a contingency reserve. What should you do FIRST?