PMP People — Leading Projects • Set 14
PMP People — Leading Projects Practice Test 14 — 15 questions with explanations. Free, no signup.
You are the project manager for a construction project. A key vendor notifies you that they cannot deliver a critical component on time, which will delay the project by at least two weeks. The vendor was already on the risk register with a contingency plan. What should you do first?