Refer to the exhibit. As a Scrum Master, what is your primary concern regarding the Scrum Team's effectiveness?
The Product Owner must be available to Developers for refinement and questions. Without this interaction, the team may build features that do not meet customer needs. This is a systemic failure in the Scrum Team's collaboration that the Scrum Master must address to ensure the product remains valuable and relevant.
Why this answer
The exhibit shows a critical disconnect between the Product Owner and the Developers. Effective Product Backlog management requires consistent collaboration. When a Product Owner is absent from the Daily Scrum and limits refinement to only two hours, the Developers lose the business context necessary to build the right thing.
This lack of engagement threatens the team's ability to deliver actual value, regardless of their stable velocity.
Exam trap
Candidates often focus on the Developers' performance or velocity rather than the root cause, which is the lack of Product Owner engagement and guidance during the refinement process.