CCNA Scrum Team Roles and Accountabilities Questions

49 questions · Scrum Team Roles and Accountabilities · All types, answers revealed

1
MCQmedium

Refer to the exhibit. As a Scrum Master, what is your primary concern regarding the Scrum Team's effectiveness?

A.The velocity is too low for the size of the team.
B.The Scrum Master is not resolving enough impediments.
C.The Product Owner is failing to provide necessary support for backlog refinement and collaboration.
D.The Developers are not taking enough responsibility for the product vision.
AnswerC

The Product Owner must be available to Developers for refinement and questions. Without this interaction, the team may build features that do not meet customer needs. This is a systemic failure in the Scrum Team's collaboration that the Scrum Master must address to ensure the product remains valuable and relevant.

Why this answer

The exhibit shows a critical disconnect between the Product Owner and the Developers. Effective Product Backlog management requires consistent collaboration. When a Product Owner is absent from the Daily Scrum and limits refinement to only two hours, the Developers lose the business context necessary to build the right thing.

This lack of engagement threatens the team's ability to deliver actual value, regardless of their stable velocity.

Exam trap

Candidates often focus on the Developers' performance or velocity rather than the root cause, which is the lack of Product Owner engagement and guidance during the refinement process.

2
Multi-Selecthard

Which TWO of the following describe a responsibility of the Scrum Master regarding the Developers?

Select 2 answers
A.Assigning specific tasks to Developers to ensure the Sprint Goal is met.
B.Coaching the team in organizational environments in which Scrum is not yet fully adopted.
C.Removing impediments to the Developers' progress.
D.Approving the final Increment at the end of the Sprint.
E.Managing the daily schedule of each Developer to track individual utilization.
AnswersB, C

Scrum Masters act as change agents within the organization. They coach the team and the broader organization on how to effectively work within the Scrum framework, even when the surrounding culture is resistant. This helps create an environment where the Developers can maximize their productivity and team health.

Why this answer

The Scrum Master serves the Scrum Team by coaching the Developers in self-management and cross-functionality. By facilitating sessions and removing impediments, the Scrum Master helps the team increase its effectiveness. These responsibilities are critical for building a high-performing team that can navigate complex work without needing external command-and-control management, which is essential for long-term project success and agility.

Exam trap

Candidates often select options involving 'managing' the team or 'assigning' tasks. The Scrum Master never manages the Developers or their work; they only coach and remove impediments.

3
MCQmedium

During a Sprint, a stakeholder approaches a Developer and asks them to add a small but urgent feature to the current Sprint Backlog. What is the most appropriate action for the Developer?

A.Accept the feature if it takes less than two hours to complete.
B.Ask the Scrum Master to update the Sprint Backlog to include the new feature.
C.Direct the stakeholder to discuss the request with the Product Owner.
D.Add the feature to the Sprint Backlog and inform the Product Owner later.
AnswerC

This approach preserves the Product Owner’s role as the person accountable for maximizing value and managing the Product Backlog. By routing the request through the Product Owner, the team ensures the new item is evaluated against existing priorities and added to the backlog appropriately for future planning.

Why this answer

The Developer must protect the integrity of the Sprint Goal and the Scrum process by referring the stakeholder to the Product Owner. The Product Owner is solely accountable for managing the Product Backlog and negotiating scope with stakeholders. This maintains the team's focus and ensures the Product Owner remains the single source of truth for work priorities, preventing scope creep and unmanaged disruptions.

Exam trap

Many candidates believe developers should accommodate urgent stakeholder requests directly to be helpful, forgetting that bypassing the Product Owner disrupts the Sprint Backlog and undermines backlog management.

4
MCQhard

A new Developer joins the team and asks the Scrum Master to explain who is responsible for the final decisions on the product's release date. What should the Scrum Master say?

A.The Scrum Team decides collectively by a majority vote.
B.The Product Owner holds the final responsibility.
C.The Stakeholders decide at the Sprint Review.
D.The Scrum Master manages the release calendar.
AnswerB

The Product Owner is the sole person accountable for the product's outcome and the release strategy. They balance stakeholder needs, team capacity, and market timing. While they consult the team, the final decision rests with them to ensure consistency and clear ownership of value delivery.

Why this answer

The Product Owner holds the accountability for the release strategy and decision-making. Since the Product Owner manages the Product Backlog and maximizes value, they decide when and what to release. The Scrum Master must clarify this accountability to ensure the team understands their roles and maintains focus on their respective domains, preventing confusion about authority within the team.

Exam trap

Candidates often believe the Scrum Master or the entire team makes the release decision, missing the fact that the Product Owner is the sole person accountable for value and release decisions.

5
Multi-Selectmedium

A Scrum Team is reviewing the accountabilities that belong to the Scrum Master. Which TWO of the following are Scrum Master accountabilities? (Choose two.)

Select 2 answers
A.Deciding which Product Backlog items the Developers will select for the next Sprint.
B.Writing the acceptance criteria for every user story to ensure consistent quality.
C.Helping the Scrum Team focus on creating high-value Increments that meet the Definition of Done.
D.Ensuring that all Scrum events take place and are positive, productive, and kept within the timebox.
E.Ordering the Product Backlog to maximize the value delivered by the Scrum Team.
AnswersC, D

The Scrum Master serves the team partly by helping it focus on high-value Increments that meet the Definition of Done. This is coaching and facilitation work that supports the team's effectiveness. It is distinct from the Product Owner's accountability for value ordering, because here the Scrum Master enables focus rather than deciding what is valuable.

Why this answer

The Scrum Master serves the Scrum Team by ensuring Scrum events are held, productive, and timeboxed, and by helping the team focus on high-value Increments that meet the Definition of Done. Ordering the backlog, selecting items, and authoring acceptance criteria belong to the Product Owner or the Developers, not to the Scrum Master.

Exam trap

The trap here is confusing the Scrum Master's coaching and event-facilitation accountabilities with the Product Owner's backlog ordering and the Developers' work-selection authority.

6
MCQmedium

If a Scrum Team finds that their Definition of Done is no longer sufficient to ensure quality, who is responsible for updating it?

A.The Scrum Master.
B.The Product Owner.
C.The Scrum Team.
D.The Developers.
AnswerC

The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product. The Scrum Team is collectively responsible for defining it. This shared accountability ensures that the quality expectations are understood and applied by everyone involved in the delivery.

Why this answer

The Scrum Team as a whole is responsible for the Definition of Done. As they learn more, they must adapt their quality standards. Updating the Definition of Done is an act of inspection and adaptation.

This shared responsibility ensures that all team members are aligned on what 'high quality' means and are committed to maintaining that standard throughout the project duration.

Exam trap

Candidates often assume only the developers or a QA lead can modify the Definition of Done, overlooking that the entire Scrum Team owns quality standards.

7
MCQeasy

In the Scrum framework, how should a team handle a conflict between two Developers regarding a technical approach?

A.Ask the Product Owner to choose the better approach.
B.The Scrum Master makes the final technical decision.
C.The Developers collaborate to reach a consensus or experiment to find the best solution.
D.The team should vote, and the majority choice is implemented.
AnswerC

This approach honors the self-management of the team. By working together to reach a consensus, the Developers ensure that the chosen solution is understood and supported by the team. This improves quality and builds team cohesion, which is fundamental to the long-term success of any Scrum implementation.

Why this answer

The team should use self-management to resolve the conflict internally. Since the Developers are accountable for the technical quality of the Increment, they must decide the best approach. If they cannot resolve it, the Scrum Master can facilitate a session, but ultimately the team must own the decision.

This fosters ownership and maturity, ensuring the team functions as a unified, collaborative unit rather than waiting for external instructions.

Exam trap

Candidates often think the Scrum Master should decide the technical approach or mediate every disagreement. This violates the principle of team self-management and slows down the team's progress.

8
MCQhard

A Product Owner is planning to attend a Sprint Retrospective to explain why the Sprint Goal was not met and to assign action items to the Developers. How should the Scrum Master respond?

A.Allow the Product Owner to attend and assign action items, since the Product Owner is accountable for value.
B.Explain that the Retrospective is for the Scrum Team to inspect and adapt its own processes, and the Product Owner may attend if invited but should not assign actions.
C.Cancel the Retrospective and hold a separate meeting with the Product Owner to discuss the missed Sprint Goal.
D.Invite the Product Owner to lead the Retrospective and define the improvement actions for the next Sprint.
AnswerB

The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements. The Scrum Master ensures the event is positive and productive, and that the team owns its improvement actions. The Product Owner may attend if invited by the team, but should not impose action items, as that would conflict with self-management.

Why this answer

The Sprint Retrospective is for the Scrum Team to inspect itself and plan improvements; the Scrum Master ensures it is positive and productive. The Product Owner may attend if invited but should not assign action items or lead the event, as that would undermine the team's self-management and ownership of its process improvement.

Exam trap

The trap here is assuming the Product Owner can direct the Retrospective because of their value accountability, when the event is owned by the Scrum Team for self-improvement.

9
Multi-Selectmedium

A Scrum Team is preparing for its first Sprint. The Product Owner insists on attending every Daily Scrum to ensure the Developers stay aligned with business priorities. The Scrum Master wants to clarify the accountabilities defined in the Scrum Guide. Which TWO statements correctly describe the Scrum Master's accountability in this situation? (Choose two.)

Select 2 answers
A.The Scrum Master should escalate the Product Owner's behavior to senior management so they can enforce the Scrum Guide.
B.The Scrum Master ensures that the Daily Scrum occurs, but the Developers are accountable for conducting it and may invite others if it serves their purpose.
C.The Scrum Master is accountable for the Scrum Team's effectiveness and should coach the Product Owner on why daily attendance may not be necessary.
D.The Scrum Master must remove the Product Owner from the Daily Scrum because only Developers may attend the event.
E.The Scrum Master is accountable for the Product Backlog and can decide which stakeholders may attend Scrum events.
AnswersB, C

The Scrum Master is accountable for the Scrum Team's effectiveness and for ensuring Scrum events take place. However, the Developers own the Daily Scrum and decide its format and attendees. The Scrum Master should coach the Product Owner rather than mandate exclusion, but the event itself belongs to the Developers.

Why this answer

The Scrum Master serves the Scrum Team by ensuring Scrum is understood and enacted, and by coaching team members and the organization. The Daily Scrum belongs to the Developers, who may invite others if it helps them inspect progress toward the Sprint Goal. The Scrum Master's response is to coach the Product Owner on the event's purpose, not to bar attendance or escalate.

Exam trap

The trap here is assuming the Scrum Master controls who may attend Scrum events, when in fact the Developers own the Daily Scrum and may invite others.

10
MCQeasy

Who is accountable for creating the Sprint Backlog?

A.The Product Owner.
B.The Scrum Team as a whole.
C.The Developers.
D.The Scrum Master.
AnswerC

The Developers are solely accountable for creating and maintaining the Sprint Backlog. This plan is theirs to manage, update, and follow. By owning the Sprint Backlog, they ensure they are committed to the work they have planned, which is a fundamental aspect of self-management in the Scrum framework.

Why this answer

The Sprint Backlog is the plan by and for the Developers. While the Product Owner defines the goal and items, the Developers decide how to achieve that goal and create the plan. This ownership is crucial for self-management, as it empowers the team to commit to work they believe they can complete, fostering accountability and high-quality results throughout the Sprint.

Exam trap

Many candidates mistakenly believe the Product Owner creates the Sprint Backlog because they own the Product Backlog. However, the Sprint Backlog is exclusively the plan for and by the Developers.

11
MCQeasy

Who is responsible for ensuring the Scrum Team adheres to the Scrum framework as defined in the Scrum Guide?

A.The Product Owner
B.The Developers
C.The Scrum Master
D.The Organization's Management
AnswerC

The Scrum Master is the primary advocate and guardian of the Scrum framework. They coach the team and organization to ensure Scrum events, artifacts, and accountabilities are respected, which prevents the team from drifting into non-Scrum practices that could hinder transparency and empirical process control.

Why this answer

The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. This accountability is critical because it ensures the team maintains the transparency, inspection, and adaptation required for empirical process control, which ultimately leads to higher team performance and value delivery.

Exam trap

Test-takers frequently think the Project Manager or the entire Scrum Team is responsible for enforcing Scrum, confusing team collaboration with the Scrum Master's specific accountability.

12
MCQmedium

In the context of the Scrum Team, what is the best definition of 'self-managing'?

A.The team chooses their own projects and clients.
B.The team determines internally how to perform their work.
C.The Scrum Master manages the daily tasks of Developers.
D.The team is allowed to ignore the Definition of Done.
AnswerB

Self-management allows the team to decide the best technical approach, task distribution, and daily processes. This autonomy enables the team to adapt quickly to changes and solve problems efficiently without waiting for external approval from managers or outside stakeholders.

Why this answer

Self-managing means the team decides who does what, when, and how. This represents a shift from traditional command-and-control management to a model where the team members take collective responsibility for their work. This is essential for Scrum because it empowers those closest to the work to make the best technical decisions, leading to faster innovation and higher quality outcomes.

Exam trap

Candidates frequently confuse 'self-managing' with 'self-organizing' or assume it means the team can ignore organizational policies, whereas it specifically refers to the team's internal authority over their own work execution.

13
MCQmedium

A Scrum Team is midway through a Sprint when a Developer realizes that a new library would significantly simplify a feature. The library is not mentioned in the Sprint Backlog. What should the Developer do?

A.Ask the Product Owner to add the library to the Product Backlog before using it.
B.Add the library to the Sprint Backlog and proceed, since the Sprint Backlog is owned by the Developers.
C.Escalate to the Scrum Master so the Scrum Master can decide whether the library is allowed.
D.Wait until the Sprint Review to propose the library for the next Sprint.
AnswerB

The Developers own the Sprint Backlog and may adapt it at any time during the Sprint as they learn more. Introducing a library that simplifies work is a technical decision within their self-managing scope. No external approval is required, provided the change does not violate the Sprint Goal or the Definition of Done.

Why this answer

The Developers are self-managing and own the Sprint Backlog, so they decide how to build the Increment. Adopting a simplifying library is an implementation choice within their authority, as long as the Sprint Goal and Definition of Done remain intact. No Product Owner approval or Scrum Master ruling is required for such a technical decision.

Exam trap

The trap here is assuming the Product Owner must approve every change made during a Sprint, when technical decisions inside the Sprint belong to the self-managing Developers.

14
MCQmedium

A team has a Product Owner who is constantly absent and rarely provides feedback. What is the Scrum Master's best approach?

A.Take over the Product Owner's duties until they return.
B.Coach the Product Owner on the impact of their engagement.
C.Report the Product Owner to HR for disciplinary action.
D.Lower the team's velocity to match the lack of guidance.
AnswerB

Coaching is the primary tool for the Scrum Master. By highlighting how the absence hinders the team's progress and the product's value, the Scrum Master helps the Product Owner see the importance of their role. This professional dialogue is the first step in resolving the impediment.

Why this answer

The Scrum Master must facilitate a conversation with the Product Owner about the impact of their absence on the team's ability to deliver. If the issue persists, the Scrum Master should escalate the impediment to management, as a non-engaged Product Owner is a critical blocker to the success of the Scrum Team and the product's value delivery.

Exam trap

Candidates often jump to replacing the PO immediately. The first step for a Scrum Master is always to coach the individual and address the impact of their behavior.

15
MCQhard

A Developer frequently misses the Daily Scrum to work on 'urgent' tasks assigned by a functional manager outside the Scrum Team. As the Scrum Master, what is your best course of action?

A.Ask the Product Owner to speak with the functional manager.
B.Coach the Developer and the organization on the importance of the team's focus and self-management.
C.Update the Sprint Backlog to account for the time the Developer spends on these tasks.
D.Remove the Developer from the team for non-compliance with the team's rules.
AnswerB

This is the correct approach because it addresses the root cause: a lack of understanding of Scrum roles and accountabilities. The Scrum Master must educate the functional manager on how their interventions disrupt the team, ensuring the Developers can remain focused on the Sprint Goal without external, unplanned interruptions.

Why this answer

The Scrum Master must protect the team from external interference that disrupts the Scrum process. This situation is a classic case of lack of organizational support for the Scrum structure. By coaching the organization and the Developer, the Scrum Master helps align stakeholders on the benefits of the team's focus and the importance of the Sprint Goal over individual, siloed tasks.

Exam trap

Candidates often suggest the Scrum Master should simply tell the developer no or ignore the functional manager. This ignores the organizational culture and the need for systemic change.

16
MCQeasy

Who holds the final authority for determining the order of items within the Product Backlog in a Scrum environment?

A.The entire Scrum Team through unanimous consensus during Sprint Planning sessions.
B.The Product Owner, incorporating feedback from stakeholders, customers, and the Scrum Team.
C.The Scrum Master after facilitating alignment workshops with organizational executives.
D.The Development Team based purely on technical dependencies and architectural complexity.
AnswerB

The Product Owner holds sole accountability for Product Backlog ordering, satisfying Scrum's single-authority constraint. Stakeholder, customer and Scrum Team input informs their decisions, but final prioritisation authority rests with the Product Owner alone. This preserves clear ownership and prevents competing priorities from fragmenting backlog order.

Why this answer

The Product Owner is solely responsible for maximizing product value and managing the Product Backlog. Their decisions regarding ordering reflect stakeholder input, market analysis, and strategic vision. This matters because a single decision-maker prevents conflicting priorities from paralyzing the Development Team during sprint execution and planning.

Exam trap

Candidates often think the Scrum Team or stakeholders vote on the order. While the PO gathers input from them, the final authority and decision-making power rest solely with the PO.

17
MCQhard

During a Sprint Review, a key stakeholder expresses dissatisfaction with the Increment's functionality and demands that the Developers immediately start working on a new feature that was not in the Sprint Backlog. The Product Owner is present. How should the Scrum Master respond?

A.Tell the stakeholder that they must submit a formal change request to the Scrum Master for approval.
B.Ignore the stakeholder's demand and continue the Sprint Review as planned without addressing the concern.
C.Explain that the Sprint Review is for gathering feedback, and the Product Owner will consider the new feature for the next Sprint Planning.
D.Ask the Developers to stop their current work and begin the new feature immediately to satisfy the stakeholder.
AnswerC

The Scrum Master should clarify the purpose of the Sprint Review and ensure the stakeholder understands that new requests are handled by the Product Owner for future Sprints. This protects the current Sprint and respects the Product Owner's accountability for ordering the Product Backlog. It also keeps the focus on inspecting the Increment and adapting the backlog.

Why this answer

The Sprint Review is a working session for inspecting the Increment and adapting the Product Backlog. New requests should be directed to the Product Owner for consideration in future Sprints. The Scrum Master should facilitate this understanding and protect the Developers from mid-Sprint disruptions, ensuring the Sprint Goal remains intact.

Exam trap

The trap here is thinking the Scrum Master should either immediately accommodate the stakeholder or act as an approval authority, rather than redirecting the request to the Product Owner for backlog consideration.

18
MCQeasy

During Sprint Planning, the Product Owner demands that the Development Team commit to a specific set of items to meet a quarterly company milestone. What is the most appropriate action for the Scrum Master?

A.Support the Product Owner by enforcing the quarterly milestone as a binding team commitment.
B.Educate both parties that the Development Team forecasts its capacity and pulls work iteratively.
C.Realign the Product Backlog items into smaller tasks so the team can absorb the extra pressure.
D.Take over Sprint Planning facilitation and unilaterally assign tasks to balance the workload.
AnswerB

The Scrum Master acts as a coach to ensure all roles understand their boundaries within the framework. Clarifying that the team creates a forecast rather than a rigid commitment preserves sustainable pacing and genuine accountability.

Why this answer

The Scrum Master must protect the integrity of the Scrum framework by clarifying that the Development Team alone estimates and pulls work. Product Owners manage value, not capacity. This distinction matters because forcing arbitrary commitments destroys morale and distorts forecasting metrics.

Exam trap

Many candidates believe the Product Owner or management can force a commitment to meet external milestones, ignoring that the Development Team forecasts its own capacity.

19
MCQeasy

A Scrum Master notices that the Developers have stopped attending the Daily Scrum because they feel it is just a status meeting for the manager. What should the Scrum Master do to help the team get value from the event?

A.Teach the Developers that the Daily Scrum is for inspecting progress toward the Sprint Goal and adapting the Sprint Backlog.
B.Attend every Daily Scrum and take detailed notes to share with management.
C.Cancel the Daily Scrum and replace it with an asynchronous written update.
D.Ask the manager to set clear daily task assignments before each Daily Scrum.
AnswerA

The Daily Scrum exists so Developers can inspect progress toward the Sprint Goal and adapt the Sprint Backlog. When the team sees it as a status report, the Scrum Master should coach them on its true purpose and help them own the event. This aligns with the Scrum Master's accountability for establishing Scrum as defined in the Scrum Guide.

Why this answer

The Daily Scrum is a 15-minute event for the Developers to inspect progress toward the Sprint Goal and adapt the Sprint Backlog. When the team views it as a status report, the Scrum Master should coach them on its purpose and help them self-manage the event, thereby restoring its value and aligning with Scrum theory.

Exam trap

The trap here is believing the Daily Scrum can be replaced or cancelled when it feels unproductive, when the Scrum Master should instead coach the team on its purpose.

20
MCQmedium

Which of the following best describes the Product Owner's accountability for the Product Backlog?

A.They must write every user story personally to ensure quality.
B.They are responsible for the implementation details of the backlog items.
C.They have the final say on the ordering of the Product Backlog.
D.They must update the Product Backlog every time a Developer suggests a change.
AnswerC

The Product Owner is accountable for the ordering of the Product Backlog. This allows them to maximize the value produced by the Scrum Team. By having authority over the order, they ensure that the team is always working on the most important goals, aligning technical output with overall business objectives.

Why this answer

The Product Owner is the sole person responsible for managing the Product Backlog. This includes clearly expressing items, ordering them, and ensuring the backlog is transparent, visible, and understood. This accountability is vital because it creates a single source of truth for what the team should build next, preventing confusion and ensuring the team always works on the highest-value items first.

Exam trap

Candidates often think management or stakeholders dictate backlog order, confusing organizational priority with the Product Owner's absolute accountability for ordering the Product Backlog.

21
MCQeasy

Which of the following is true about the Scrum Master's role during the Sprint Retrospective?

A.The Scrum Master decides which improvements the team will implement.
B.The Scrum Master ensures the event is held and facilitates it as requested.
C.The Scrum Master reports the team's failures to management.
D.The Scrum Master writes the improvement plan for the next Sprint.
AnswerB

The Scrum Master is responsible for ensuring the Retrospective is held and that it is productive. By facilitating, they help the team surface issues and generate actionable improvements. This structure ensures that the team continuously improves their process, which is a cornerstone of the empirical nature of Scrum.

Why this answer

The Scrum Master facilitates the Retrospective to ensure it is positive, productive, and focused on improvement. They do not own the improvements; the team does. By facilitating the meeting, the Scrum Master helps the team inspect their process and identify ways to become more effective in the next Sprint, which is the primary goal of the Retrospective event in Scrum.

Exam trap

Candidates often assume the Scrum Master must provide the solutions or own the improvements. The Scrum Master only facilitates the event; the team owns the process and the improvements.

22
MCQhard

A Scrum Master notices that the Developers and the Product Owner have conflicting views on the priority of technical debt versus new features. The Developers want to allocate 30% of each Sprint to refactoring, but the Product Owner insists on delivering only customer-facing features. The Scrum Master wants to help resolve this conflict. What is the most appropriate action?

A.Advise the Developers to work on technical debt without informing the Product Owner to avoid conflict.
B.Escalate the conflict to senior management to decide the appropriate allocation of effort.
C.Facilitate a conversation between the Developers and the Product Owner to help them understand each other's perspectives and find a balanced approach.
D.Instruct the Product Owner to allocate 30% of each Sprint to technical debt because it is essential for long-term quality.
AnswerC

The Scrum Master serves the Scrum Team by facilitating collaboration and removing impediments. Helping the Developers and Product Owner communicate and negotiate a solution aligns with this accountability. The Scrum Master does not decide the priority but ensures the team can self-manage and make informed decisions together, preserving both value delivery and technical health.

Why this answer

The Scrum Master serves the Scrum Team by facilitating collaboration and helping members resolve conflicts. Facilitating a conversation allows the Developers and Product Owner to understand each other's concerns and jointly decide on an approach that balances feature delivery with technical health. This respects the Product Owner's accountability for value and the Developers' need for sustainable pace.

Exam trap

The trap here is thinking the Scrum Master should make the decision or escalate, rather than facilitating a collaborative resolution between the Developers and Product Owner.

23
MCQhard

During a Sprint, the Scrum Master notices that the Developers keep waiting for the Product Owner to assign tasks and resolve every technical disagreement. Which action best reflects the Scrum Master's accountability?

A.Coach the Scrum Team on self-management and facilitate the removal of the dependency on the Product Owner for technical decisions.
B.Instruct the Product Owner to stop assigning tasks and let the Developers self-organize.
C.Take over assigning tasks temporarily so the Sprint is not delayed, then hand control back later.
D.Raise the issue at the Sprint Retrospective only, and take no action during the current Sprint.
AnswerA

The Scrum Master serves the Scrum Team by coaching it in self-management and helping it focus on creating high-value Increments. Here the team is not exercising its authority over technical work, so the Scrum Master should coach the team and address the underlying dependency, enabling the Developers to make their own technical decisions.

Why this answer

The Scrum Master serves the Scrum Team by coaching it in self-management and helping it focus on high-value Increments. When Developers defer every technical choice to the Product Owner, the Scrum Master should coach the team and remove that dependency, restoring the Developers' authority over how they do their work rather than issuing orders or taking over.

Exam trap

The trap here is thinking the Scrum Master should direct people or take over tasks, when the accountability is to coach self-management and remove impediments.

24
MCQhard

Refer to the exhibit. According to the Scrum Guide, which answer is correct?

A.The testers.
B.The Product Owner.
C.The Developers.
D.The Scrum Team.
AnswerD

The entire Scrum Team is responsible for the product's quality. This includes adhering to the Definition of Done, which is a team-wide agreement. Shared accountability ensures that no single person or sub-group is solely blamed or praised, fostering a collaborative and high-quality development culture.

Why this answer

The Scrum Team, as a single unit, is accountable for creating a quality increment. While individual members have different skills, the responsibility for the Definition of Done and the quality of the final product rests with the team as a whole. This shared accountability encourages collaboration and prevents the siloing of quality as 'someone else's job,' which is a common failure point in traditional teams.

Exam trap

Test-takers often assign quality and the Definition of Done exclusively to testers or the Scrum Master, forgetting that the entire Scrum Team shares this accountability.

25
MCQeasy

A newly formed Scrum Team is clarifying who does what. The Developers ask who is accountable for creating a clear, ordered Product Backlog that maximizes the value the product delivers. Which accountability fits best?

A.The Product Owner, who is accountable for the Product Backlog and its effective management.
B.The stakeholders, because they provide the requirements and business priorities.
C.The Scrum Master, because they facilitate all Scrum events and remove impediments.
D.The Developers, because they estimate and select the work they will complete each Sprint.
AnswerA

The Product Owner is accountable for maximizing product value and for effective Product Backlog management, including clearly expressing items and ordering them. This is a defining accountability in the Scrum Guide, so the Developers should look to the Product Owner for backlog clarity and ordering.

Why this answer

The Product Owner is accountable for the Product Backlog, including its content, availability, and ordering. This single accountability ensures the team always works on the most valuable items. The Scrum Master facilitates, the Developers deliver, and stakeholders inform, but only the Product Owner owns backlog clarity and order.

Exam trap

The trap here is thinking that because stakeholders provide requirements, they also control backlog ordering.

26
MCQhard

Midway through a Sprint, a Developer identifies that a technical approach will not meet the Sprint Goal and proposes a different design. The Product Owner is concerned about scope but trusts the team. According to Scrum, how should this situation be handled?

A.The change must wait until the Sprint Review, because the Sprint Backlog is frozen once the Sprint begins.
B.The Product Owner must approve the new design before any change, since they are accountable for the value delivered.
C.The Scrum Master should decide, because they are accountable for removing impediments and ensuring the Sprint Goal is met.
D.The Developers should adjust their plan and approach, because they self-manage how to turn Product Backlog items into an Increment of value.
AnswerD

Developers are accountable for organizing their own work and for the technical decisions needed to create the Increment. Changing the approach mid-Sprint to meet the Sprint Goal is exactly what self-management means. The Product Owner focuses on value and scope, while the Developers determine how to build the product.

Why this answer

Developers are accountable for managing and adapting their own work, including the technical approach. The Sprint Backlog is a living plan that can change at any time during the Sprint. The Product Owner may discuss scope and value, but the how belongs to the Developers, who are best positioned to make design decisions.

Exam trap

The trap here is treating the Sprint Backlog as a frozen contract that only the Product Owner can change.

27
Multi-Selectmedium

Which TWO of the following are true about the Scrum Master's role?

Select 2 answers
A.The Scrum Master is responsible for the team's final output quality.
B.The Scrum Master serves the Product Owner by helping them find techniques for effective Product Backlog management.
C.The Scrum Master manages the daily calendar of every team member.
D.The Scrum Master is responsible for the team's effectiveness.
E.The Scrum Master directs the Developers on the best ways to write code.
AnswersB, D

The Scrum Master serves the Product Owner in several ways, including helping them find techniques to manage the backlog, facilitating stakeholder collaboration, and ensuring the PO understands the need for clear, concise items. This support is crucial for the PO to be effective at maximizing value for the stakeholders.

Why this answer

The Scrum Master is a servant-leader who focuses on the team, Product Owner, and organization. By ensuring that the Scrum framework is understood and enacted, they create an environment where high-quality work is possible. These dual roles—improving the process and removing blockers—are essential to ensure that the Scrum Team remains effective and that the organization values the agility that Scrum provides.

Exam trap

Test-takers often select options that give the Scrum Master authority over people or technical output, confusing servant-leadership with line management responsibilities.

28
Multi-Selectmedium

Which THREE of the following are responsibilities that fall under the Scrum Master's accountability toward the Scrum Team?

Select 3 answers
A.Coaching the team in self-management and cross-functionality.
B.Ordering the Product Backlog items to maximize value.
C.Helping the team focus on creating high-value increments.
D.Removing impediments to the Scrum Team's progress.
E.Writing the user stories for the Product Backlog.
AnswersA, C, D

Helping a team move toward self-management is a core duty. A team that manages its own work is more resilient and adaptable. Cross-functionality ensures that the team has all the skills necessary to turn Product Backlog items into a Done increment without external dependencies slowing them down.

Why this answer

The Scrum Master acts as a servant-leader for the Scrum Team. These specific responsibilities focus on removing impediments, coaching the team on self-management, and ensuring that all Scrum events take place and are productive. By focusing on these areas, the Scrum Master enables the team to maintain high velocity and quality while adhering to the core principles of the Scrum framework.

Exam trap

Candidates frequently select tasks that sound like 'managing the team' or 'assigning work,' which contradicts the servant-leadership and self-management principles at the heart of the Scrum Master's role.

29
MCQeasy

A Scrum Team is preparing for its first Sprint. The organization asks who is accountable for establishing the Scrum Team's Definition of Done if the organization has no existing standard. Who should create it?

A.The stakeholders, because they determine what quality means for the product.
B.The Product Owner, because the Definition of Done affects product quality.
C.The Developers, because they create the Increment and define the quality standard it must meet.
D.The Scrum Master, because the Scrum Master owns all Scrum processes.
AnswerC

If the organization has no standard, the Developers must create a Definition of Done appropriate for the product. They produce the Increment each Sprint, so they define the quality bar it must satisfy. This artifact makes the work transparent and is used to verify the Increment, and the Developers own its creation.

Why this answer

When no organizational standard exists, the Developers must create a Definition of Done suitable for the product. Because they build the Increment, they define the quality criteria it must meet, making the work transparent and verifiable. The Product Owner and Scrum Master participate as team members but do not own this artifact.

Exam trap

The trap here is attributing the Definition of Done to the Scrum Master or Product Owner, when the Developers are accountable for creating it when no organizational standard exists.

30
MCQhard

A Scrum Team has two Product Owners to handle the complex, multi-departmental product. What is the most common issue this creates regarding Scrum accountability?

A.Increased velocity due to double the input.
B.Ambiguity in decision-making and backlog ordering.
C.A violation of the Scrum Master's role.
D.The team becomes too cross-functional.
AnswerB

A single Product Owner is necessary to provide clear, unified direction. When two people share the role, backlog ordering becomes inconsistent, causing the team to lose focus. This lack of a single point of accountability makes it impossible to effectively maximize value, a core tenet of Scrum.

Why this answer

Scrum defines the Product Owner as one person, not a committee. Having two Product Owners creates confusion over who has the final authority to prioritize the Product Backlog, leading to conflicting instructions for Developers and reduced transparency. This ambiguity prevents the team from having a single, clear source of value optimization, which is essential for effective decision-making and focus in a Scrum environment.

Exam trap

Candidates often assume that having multiple Product Owners is acceptable if the product is large or complex, failing to recognize that Scrum strictly mandates a single person to ensure accountability and clear prioritization.

31
MCQmedium

During a Sprint, a stakeholder approaches a developer directly and asks for a small urgent modification to a user story currently in progress. What is the most appropriate action for the developer to take?

A.Implement the modification immediately if it takes less than an hour to avoid unnecessary bureaucratic delay for the stakeholder.
B.Bring the request to the next Daily Scrum so the entire Scrum Team can vote on whether to swap out an existing backlog item.
C.Direct the stakeholder to discuss the request with the Product Owner so it can be evaluated, prioritized, and added to the Product Backlog.
D.Halt the current Sprint immediately, call an emergency Sprint Planning session, and rebuild the Sprint Backlog with the new requirement.
AnswerC

The Product Owner owns the Product Backlog and must evaluate all new scope requests. They decide whether the item merits inclusion in a future Sprint based on value, dependencies, and overall product strategy without disrupting current execution.

Why this answer

The developer should direct the stakeholder to the Product Owner, who is exclusively accountable for managing product backlog items and their ordering. Developers must protect the Sprint Backlog from mid-Sprint scope changes introduced outside the Scrum Team to maintain focus on the Sprint Goal. Engaging directly without the Product Owner risks undermining team predictability and introduces unmanaged scope creep into the active iteration.

Exam trap

Candidates often assume developers should be accommodating and helpful to stakeholders, forgetting that bypassing the Product Owner disrupts the established workflow and violates accountability boundaries within the Scrum framework.

32
MCQeasy

What is the primary role of the Scrum Master during the Sprint Planning event?

A.Assigning tasks to the Developers.
B.Facilitating the event and ensuring it stays within the timebox.
C.Defining the Sprint Goal for the team.
D.Writing the user stories for the backlog.
AnswerB

Facilitation is the core duty of the Scrum Master during events. By managing the timebox and keeping the discussion focused, they ensure that the team produces a meaningful Sprint Backlog and Sprint Goal without the meeting dragging on, which helps maintain high team morale and efficiency.

Why this answer

The Scrum Master ensures that the Sprint Planning event takes place and that its purpose is understood. They facilitate the process, ensuring the team stays within the timebox and focuses on defining the Sprint Goal and the plan for the Sprint. This keeps the team focused and ensures that planning is efficient, collaborative, and grounded in the Scrum framework's values.

Exam trap

Candidates often think the Scrum Master is responsible for the actual planning or task breakdown, confusing the role of facilitator with that of a team member.

33
Multi-Selectmedium

Which TWO of the following are considered accountabilities of the Developers in a Scrum Team?

Select 2 answers
A.Creating a plan for the Sprint, the Sprint Backlog.
B.Defining the product vision and roadmap.
C.Holding each other accountable as professionals.
D.Final approval of the Definition of Done.
E.Managing stakeholder expectations and communications.
AnswersA, C

Developers are responsible for selecting items from the Product Backlog and decomposing them into actionable tasks. This process creates the Sprint Backlog, which serves as a living document of their commitment for the Sprint, reflecting how they intend to achieve the Sprint Goal through collective effort.

Why this answer

Developers are accountable for the technical execution and quality of the increment. They must manage their own work during the Sprint to meet the Definition of Done. These accountabilities ensure that the team focuses on creating a usable, high-quality product increment every Sprint, emphasizing self-management and cross-functionality in achieving the Sprint Goal.

Exam trap

Candidates frequently pick management-related tasks or Scrum Master duties, failing to recognize that developers are entirely self-managing regarding their internal execution and professionalism.

34
MCQhard

Refer to the exhibit. What does this reveal about the team's structure and role expectations?

A.The team size is too small; they need more developers.
B.The team is not truly cross-functional, as they rely on functional hand-offs.
C.The Product Owner is not providing clear requirements for the backend work.
D.The Scrum Master failed to assign the backend work to the frontend developers.
AnswerB

True cross-functionality means the team possesses all the skills needed to complete the work without waiting on external dependencies. Having distinct 'Backend' and 'Frontend' teams within one Scrum Team suggests that they are not collaborating effectively, which leads to bottlenecks and prevents the team from finishing the Increment.

Why this answer

The team is currently operating as a collection of silos (Backend, Frontend, QA) rather than a truly cross-functional team. The fact that the frontend team is 'waiting' indicates that they lack the necessary skills within their sub-group to complete the work, or that they are not collaborating as a single unit. The team needs to cross-train to become truly cross-functional and move away from siloed thinking.

Exam trap

Test-takers frequently misinterpret functional silos as specialized efficiency, overlooking the Scrum principle that true cross-functional teams should eliminate hand-offs and waiting periods between departments.

35
MCQhard

A Scrum Team has members in three different time zones. The Product Owner is in a time zone that makes synchronous collaboration during the Daily Scrum impossible. What is the most Scrum-appropriate solution?

A.The Product Owner is not required to attend the Daily Scrum, so the team proceeds without them.
B.The Scrum Master should mandate that the Product Owner works overtime to join the call.
C.The team should replace the Daily Scrum with a daily email update.
D.The team should split into two Scrum Teams based on time zones.
AnswerA

The Daily Scrum is for the Developers to plan their work. If the Product Owner is not a Developer, their presence is not mandatory. This respects the reality of the team's constraints while keeping the focus on the Developers' collaboration, which is the actual purpose of the Daily Scrum event.

Why this answer

Scrum requires that the Scrum Team adapts to its environment while maintaining the core accountabilities and events. When synchronous meetings are difficult, the team must find a way to meet the purpose of the event—alignment and progress tracking—without necessarily relying on a rigid, live daily call. The focus must be on keeping the team informed and ensuring the work remains transparent to everyone.

Exam trap

Candidates often assume that every Scrum event requires mandatory attendance from all Scrum Team members, including the Product Owner, failing to recognize that the Daily Scrum is primarily for Developers.

36
MCQmedium

A Development Team member consistently interrupts fellow developers during Daily Scrums and pushes technical architectural changes without team consensus. What is the most appropriate Scrum Master response?

A.Escalate the developer's behavior to the functional engineering manager for a formal performance review.
B.Facilitate a private coaching session with the developer to discuss collaborative norms and active listening.
C.Facilitate the Daily Scrum personally to strictly enforce time limits and prevent anyone from speaking out of turn.
D.Remove the developer from the Scrum Team immediately to restore immediate harmony during the next sprint.
AnswerB

Private coaching targets behavioral root causes respectfully while upholding servant leadership principles. It empowers the developer to adjust their interpersonal approach without causing public embarrassment, aligning directly with the Scrum Master's core duty of team enablement.

Why this answer

The Scrum Master acts as a servant leader by facilitating self-organization and resolving impediments without taking direct command. Coaching the individual on collaborative behavior helps preserve team autonomy while addressing disruptive dynamics. This matters because a healthy Scrum Team relies on psychological safety and shared ownership rather than autocratic technical dictation by a single dominant developer.

Exam trap

Candidates often choose to escalate to management or force the developer to stop immediately. Both approaches undermine the team's self-management and psychological safety, which the Scrum Master must protect.

37
MCQmedium

During a Sprint Planning event, the Developers realize they cannot deliver all selected Product Backlog items within the timebox due to a complex technical dependency. What is the most appropriate action for the Developers to take according to Scrum?

A.Immediately appeal to management to extend the current Sprint duration to accommodate the newly discovered technical dependencies.
B.Commit to all items anyway, intending to work mandatory overtime hours to ensure complete delivery by the end of the Sprint.
C.Collaborate with the Product Owner to renegotiate and adjust the scope of the Sprint Backlog until it fits the realistic capacity.
D.Ask the Scrum Master to unilaterally remove the problematic Product Backlog items without consulting the Product Owner.
AnswerC

Collaborating with the Product Owner allows the Developers to re-evaluate the selected items and modify the Sprint Backlog so that the remaining work genuinely fits their actual capacity while still protecting the primary Sprint Goal.

Why this answer

The Developers own the Sprint Backlog and are solely responsible for estimating their capacity and crafting the Sprint Goal. When they realize capacity is insufficient, they must collaborate with the Product Owner to adjust the scope of the Sprint Backlog before finalizing the plan, ensuring the Sprint Goal remains achievable without lowering quality standards or forcing unauthorized overtime.

Exam trap

Candidates often assume the Scrum Master or Product Owner dictates the capacity changes, forgetting that the Developers alone manage their workload and must proactively renegotiate scope with the Product Owner.

38
MCQmedium

During the Sprint Retrospective, the team identifies that the Product Owner is consistently adding items to the Sprint Backlog mid-sprint. What is the correct way to address this?

A.The Developers should just ignore the new items.
B.The Scrum Master must facilitate a conversation about team focus.
C.The team should automatically increase their velocity.
D.The Developers should charge the Product Owner for overtime.
AnswerB

The Scrum Master is responsible for coaching the team on Scrum values and rules. By bringing this up at the Retrospective, the Scrum Master helps the Product Owner understand that mid-sprint changes threaten the Sprint Goal, fostering a more disciplined approach to planning and delivery.

Why this answer

The Sprint Backlog is the plan for the Sprint and should not be changed in a way that endangers the Sprint Goal. The Scrum Master must coach the Product Owner on the impact of changing the plan during the Sprint. This ensures that the team maintains a stable environment to meet their commitments and protects the integrity of the Scrum process.

Exam trap

Candidates often suggest that the team should just accept the changes or that the Product Owner has the right to change the Sprint Backlog whenever they want, ignoring the need for stability.

39
MCQmedium

An organization wants to adopt Scrum and asks who is responsible for helping employees and stakeholders understand and enact an empirical approach for complex work. Who serves this need?

A.The Product Owner, by communicating the product vision and backlog priorities to stakeholders.
B.The Scrum Master, by leading, training, and coaching the organization in its Scrum adoption.
C.An external agile coach, because Scrum adoption always requires outside expertise.
D.The Developers, by demonstrating working software and technical excellence during each Sprint.
AnswerB

The Scrum Master serves the organization by leading, training, and coaching it in Scrum adoption, and by helping employees and stakeholders understand and enact an empirical approach for complex work. This includes planning and advising on Scrum implementations and removing barriers between stakeholders and Scrum Teams.

Why this answer

The Scrum Master serves the organization by leading, training, and coaching it in Scrum adoption, helping employees and stakeholders understand and enact empiricism for complex work, and removing barriers between stakeholders and Scrum Teams. Product direction, delivery excellence, and optional external coaching do not carry this accountability.

Exam trap

The trap here is assuming an external coach or the Product Owner handles organizational Scrum education, when the Scrum Master serves the organization in that capacity.

40
MCQmedium

A Scrum Team has grown to nine Developers, and the Scrum Master observes that the team is spending too much time coordinating and too little time delivering value. What should the Scrum Master do first?

A.Recommend splitting the team into two Scrum Teams, each with its own Product Owner and Scrum Master.
B.Add a project manager to coordinate the Developers' tasks and report progress.
C.Coach the team on self-management and help them find ways to reduce coordination overhead.
D.Extend the Daily Scrum to 30 minutes to allow more coordination time.
AnswerC

The Scrum Master serves the Scrum Team by coaching on self-management and helping them improve their processes. When coordination overhead grows, the Scrum Master should first help the team inspect and adapt their own way of working, such as refining their Definition of Done or improving collaboration, rather than imposing structural changes prematurely.

Why this answer

The Scrum Master serves the Scrum Team by coaching on self-management and helping them improve their way of working. When coordination overhead increases, the Scrum Master should first help the team inspect and adapt their own practices, rather than imposing structural changes or adding management roles that conflict with Scrum principles.

Exam trap

The trap here is jumping to structural solutions like splitting the team or adding a coordinator, when the Scrum Master should first coach the team on self-management.

41
MCQmedium

A Scrum Team is struggling to deliver a potentially releasable Increment each Sprint because the Developers keep discovering integration issues late. The Scrum Master wants to help the team improve. According to Scrum, what is the most appropriate action for the Scrum Master to take?

A.Ask the Product Owner to add a backlog item for fixing integration issues in the next Sprint.
B.Instruct the Developers to adopt continuous integration and automated testing immediately.
C.Coach the Developers to improve their Definition of Done and self-manage their integration practices.
D.Escalate the problem to management so they can allocate additional resources to the team.
AnswerC

The Scrum Master serves the Scrum Team by coaching it in self-management and cross-functionality. Helping the Developers refine their Definition of Done and address integration issues themselves aligns with Scrum principles. This empowers the team to own their process and continuously improve, rather than relying on external direction.

Why this answer

The Scrum Master serves the Scrum Team by coaching it in self-management and helping it improve its practices. When integration issues arise, the most appropriate action is to guide the Developers to enhance their Definition of Done and take ownership of their integration approach. This fosters continuous improvement and aligns with Scrum's empirical nature.

Exam trap

The trap here is assuming the Scrum Master should direct technical solutions or escalate to management, rather than coaching the team to self-manage and improve its own processes.

42
MCQmedium

A Product Owner is unavailable for three consecutive Sprints due to a medical emergency. Who is responsible for managing the Product Backlog during this absence?

A.The Scrum Master takes over all Product Owner accountabilities until they return.
B.The Developers collectively decide on the priority of the Product Backlog items.
C.The organization must ensure the Product Owner accountabilities are fulfilled through temporary delegation or reassignment.
D.The Sprint remains frozen until the Product Owner returns to manage the backlog.
AnswerC

Accountability for the Product Backlog cannot simply vanish during an absence. The organization must take responsibility to ensure someone is empowered to make decisions regarding value and priority. This maintains the flow of the Scrum process and prevents the team from becoming stalled or directionless during the gap.

Why this answer

The Scrum Guide states that the Product Owner is accountable for effective Product Backlog management. If the Product Owner is unavailable, the organization must ensure this accountability is fulfilled. While others may help with the mechanics, the accountability remains with the Product Owner role or requires an explicit handover.

This ensures the team remains focused on value delivery while maintaining clarity on product direction despite unforeseen personnel changes.

Exam trap

Candidates often assume the Scrum Master takes over the Product Backlog or that the team can simply ignore it. Both are incorrect as the organization must ensure the PO's accountabilities are fulfilled.

43
Multi-Selectmedium

Which THREE of the following are considered hallmarks of a 'self-managing' Scrum Team?

Select 3 answers
A.The team chooses the most effective way to achieve the Sprint Goal.
B.The team relies on the Scrum Master to assign daily work.
C.The team members hold each other accountable for the Definition of Done.
D.The team can pivot their technical approach during the Sprint.
E.The team waits for the Product Owner to prioritize their daily tasks.
AnswersA, C, D

Self-management means the team is empowered to decide the 'how' of their work. This autonomy is crucial for innovation and problem-solving, as those closest to the technical details are best positioned to determine the most effective approach to deliver the increment within the Sprint.

Why this answer

A self-managing team takes charge of their own work, fosters internal accountability, and adapts their processes to optimize their output. These characteristics signify that the team has moved away from needing external supervision and has achieved a level of maturity where they can deliver value independently, which is the ultimate goal of the Scrum framework for teams.

Exam trap

Candidates often select options involving external reporting or manager approval, failing to realize that a self-managing team relies on internal, not external, mechanisms for accountability and decision-making.

44
MCQmedium

A senior stakeholder frequently approaches Developers during the Sprint to request 'minor' changes. What should the Developers do?

A.Implement the changes if they are small to keep the stakeholder happy.
B.Inform the stakeholder that they must discuss these requests with the Product Owner.
C.Accept the work but delay a lower-priority task in the Sprint.
D.Ask the Scrum Master to handle the stakeholder's request.
AnswerB

Directing the request to the Product Owner is the correct process. It ensures that the Product Owner can manage the work based on value and urgency while protecting the Developers from distraction. This keeps the workflow orderly and ensures that the team stays focused on their agreed-upon Sprint Goal.

Why this answer

The Developers must protect the Sprint Backlog from outside interference to ensure the Sprint Goal is met. Directing the stakeholder to the Product Owner maintains the integrity of the Scrum process. The Product Owner is the person responsible for the backlog and the value delivery, so they must assess any new requests against existing priorities and determine if they should be included in the product.

Exam trap

Candidates mistakenly choose options where developers negotiate minor changes themselves or reject them rudely, forgetting the proper channel through the Product Owner.

45
MCQmedium

If a Scrum Team finds that their Scrum Master is absent, can they still hold their Scrum events?

A.No, because the Scrum Master is required to facilitate all events.
B.Yes, but they must record the meeting for the Scrum Master to review later.
C.Yes, the Scrum Team is self-managing and can run their events.
D.No, they must reschedule all events until the Scrum Master returns.
AnswerC

Self-management means the team is capable of organizing their own work and events. If the Scrum Master is unavailable, the team should proceed as planned to maintain the rhythm and transparency of the Scrum process, demonstrating their commitment to the framework and their own productivity.

Why this answer

Scrum events are required for the Scrum Team to function, regardless of whether the Scrum Master is present. The team is self-managing and capable of facilitating their own meetings. While the Scrum Master helps ensure the events are productive, the team's commitment to the process should not depend on the presence of any one individual, reinforcing their independence and maturity.

Exam trap

Candidates often assume that Scrum events are legally void or must be canceled if the Scrum Master is absent, misunderstanding the team's ability to operate autonomously.

46
Multi-Selectmedium

Which TWO are responsibilities of the Developers during the Sprint?

Select 2 answers
A.Ensuring the Increment meets the Definition of Done.
B.Prioritizing the Product Backlog to maximize value.
C.Creating a plan for the Sprint during Sprint Planning.
D.Managing the team's budget and external vendor relationships.
E.Approving all changes requested by external stakeholders.
AnswersA, C

The Developers are responsible for creating an Increment that meets the Definition of Done. This ensures the quality remains consistent throughout the project. Without this shared standard of quality, the team cannot truly say they have delivered a valuable, potentially shippable product increment at the end of the Sprint.

Why this answer

The Developers are accountable for delivering high-quality, 'Done' work each Sprint. By managing their own progress and collaborating closely, they ensure that the Increment meets the team's definition of quality. These responsibilities are essential for the team to achieve its Sprint Goal and remain a self-managing unit that delivers consistent value to the customer.

Exam trap

Test-takers often select administrative tasks like backlog refinement or managing stakeholders as developer duties, confusing developer accountability with Product Owner responsibilities.

47
MCQmedium

A Scrum Team is struggling with a persistent lack of clarity about the scope of the Sprint. During the Sprint, Developers keep discovering work that was not discussed in Sprint Planning. Which accountability best addresses this by ensuring a clear Sprint Goal and a shared understanding of the work?

A.The Developers, who self-manage and decide how to turn Product Backlog items into a valuable Increment.
B.The entire Scrum Team, which collaboratively creates the Sprint Goal and plans the Sprint during Sprint Planning.
C.The Scrum Master, who facilitates the Scrum events and coaches the team on Scrum theory.
D.The Product Owner, who is accountable for maximizing the value of the product resulting from the work of the Scrum Team.
AnswerB

The Scrum Guide states that the Scrum Team is accountable for creating a valuable, useful Increment, and that the Sprint Goal is created collaboratively during Sprint Planning. Since the whole team owns the Sprint plan, unclear scope is best resolved by the team improving its planning and shared understanding, not by assigning sole ownership to one accountability.

Why this answer

The Sprint Goal and Sprint plan are created together by the whole Scrum Team during Sprint Planning. No single accountability owns the scope; clarity comes from collaboration. Improving shared understanding of the Sprint Goal and selected items is a team responsibility, so the entire Scrum Team is the best answer to the described lack of clarity.

Exam trap

The trap here is assuming the Product Owner alone defines the Sprint's scope, when the Sprint Goal is actually created collaboratively by the whole Scrum Team.

48
Multi-Selecthard

Which TWO of the following statements accurately describe the accountabilities of the Scrum Master regarding the Product Owner?

Select 2 answers
A.Coaching the Product Owner on effective backlog management.
B.Ensuring the Product Owner is available for every Daily Scrum.
C.Helping the Product Owner understand the need for clear Product Backlog items.
D.Approving the Product Backlog items before the Sprint.
E.Performing all product research for the Product Owner.
AnswersA, C

The Scrum Master helps the Product Owner master techniques like user story mapping or backlog prioritization. This support is vital for ensuring the team works on the most valuable items, which is a key part of the Product Owner's role in maximizing the product's value.

Why this answer

The Scrum Master serves the Product Owner by helping them find techniques for effective Product Backlog management and understanding the need for clear, concise items. This support is crucial because an effective Product Owner directly influences the team's ability to deliver value. By coaching the Product Owner, the Scrum Master ensures the entire Scrum Team operates efficiently towards the product's success.

Exam trap

Candidates often confuse the Scrum Master's role with that of a 'Business Analyst' or 'Project Manager,' suggesting the Scrum Master should write requirements or perform the work for the Product Owner.

49
MCQmedium

A Scrum Master joins a team where the Product Owner is also the line manager of several Developers. The Developers frequently wait for the Product Owner's approval before making technical decisions during the Sprint. What should the Scrum Master do first to address this?

A.Ask the Product Owner to step down as line manager so the Developers can self-manage without interference.
B.Raise the issue at the next Sprint Retrospective and let the Developers decide whether to change their behavior.
C.Instruct the Developers to stop seeking approval and make all decisions independently from now on.
D.Coach the Scrum Team and the Product Owner on the boundaries between self-management and product ownership, helping them understand that Developers own technical decisions.
AnswerD

This is correct because the Scrum Master serves the Scrum Team by coaching on self-management and serves the organization by helping it understand Scrum. Clarifying that Developers self-manage their work while the Product Owner manages the Product Backlog addresses the confusion without undermining anyone's role. It fosters an empirical, collaborative environment and respects the Scrum framework's accountabilities.

Why this answer

The Scrum Master is accountable for coaching the Scrum Team and the wider organization in Scrum theory and practice. When Developers hesitate to make technical decisions because their Product Owner is also their manager, the underlying confusion is about accountabilities. By clarifying that Developers self-manage their technical work while the Product Owner owns the Product Backlog, the Scrum Master removes an impediment and fosters the environment needed for empirical process control.

Exam trap

The trap here is assuming the Scrum Master should immediately escalate or reorganize reporting lines instead of first coaching the team and Product Owner on Scrum accountabilities.