If a Scrum Team finds that their Definition of Done is no longer sufficient to ensure quality, who is responsible for updating it?

⚠ Common exam trap

Candidates often assume only the developers or a QA lead can modify the Definition of Done, overlooking that the entire Scrum Team owns quality standards.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Scrum Team.

The Scrum Team as a whole is responsible for the Definition of Done. As they learn more, they must adapt their quality standards. Updating the Definition of Done is an act of inspection and adaptation. This shared responsibility ensures that all team members are aligned on what 'high quality' means and are committed to maintaining that standard throughout the project duration.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Scrum Master.

    Why it's wrong here

    The Scrum Master facilitates, but does not own, the definition of quality. Defining the standard of 'Done' is a team-wide responsibility. By forcing one role to define it, the team would lose the collective buy-in necessary to enforce these standards consistently during the development process.

  • ✗

    The Product Owner.

    Why it's wrong here

    The Product Owner is responsible for the Product Backlog, not the definition of quality. While they care about quality, the technical and process-based Definition of Done belongs to the team that does the work. If the PO dictated it, it might not reflect the actual technical constraints of the project.

  • ✓

    The Scrum Team.

    Why this is correct

    The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product. The Scrum Team is collectively responsible for defining it. This shared accountability ensures that the quality expectations are understood and applied by everyone involved in the delivery.

  • ✗

    The Developers.

    Why it's wrong here

    While Developers are the ones who do the work, the Definition of Done is a commitment for the whole Scrum Team. If only Developers were responsible, they might define quality in a way that ignores the Product Owner's perspective, or the PO might feel less invested in supporting the necessary quality efforts.

About these practice questions

Courseiva writes every CSM question from scratch — 312 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scrum Alliance exam blueprint

This CSM practice question is part of Courseiva's free Scrum Alliance certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CSM exam.