PMP Practice Question: Business Environment: strategy and project benefits
During a project, an executive stakeholder bypasses you and directly assigns work to your team members. This has caused confusion and rework. What is the best action for you to take?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Speak directly to the executive and explain the impact of bypassing the project manager
The project manager should communicate with the executive to clarify the proper communication channels and reinforce the project management plan. This aligns with PMI's emphasis on stakeholder engagement and communication.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Instruct the team to ignore any direct requests from the executive
Why it's wrong here
Instructing the team to ignore direct requests from an executive stakeholder is an unprofessional and counterproductive approach. This action would severely damage stakeholder relationships, create an adversarial project environment, and could lead to non-compliance, potentially jeopardizing critical project support and resources. It undermines the project manager's role in fostering collaboration and resolving issues constructively.
- ✗
Escalate the issue to the sponsor without talking to the executive first
Why it's wrong here
Escalating the issue directly to the sponsor without first engaging the executive stakeholder is a premature and potentially damaging step. Project management best practices advocate for attempting to resolve conflicts at the lowest possible level. Bypassing direct communication can strain the project manager's relationship with the executive, imply an inability to manage conflict, and unnecessarily consume the sponsor's time on matters that could be resolved peer-to-peer.
- ✗
Update the communications management plan to prohibit direct stakeholder-to-team communication
Why it's wrong here
Unilaterally updating the Communications Management Plan to prohibit direct stakeholder-to-team communication is an authoritarian and likely ineffective measure. Such a change, implemented without prior discussion and buy-in from key stakeholders, will likely be disregarded, rendering the plan moot. Effective communication planning requires collaborative development and agreement to ensure adherence and foster a cooperative environment, rather than imposing rules retroactively.
- ✓
Speak directly to the executive and explain the impact of bypassing the project manager
Why this is correct
Speaking directly to the executive and explaining the impact of bypassing the project manager is the most appropriate and proactive first step. This approach allows the project manager to understand the executive's motivations, educate them on potential risks like scope creep or resource conflicts, and collaboratively re-establish proper communication channels. It demonstrates leadership, problem-solving skills, and a commitment to maintaining project integrity and efficiency.
Go deeper
Related to this question
Learn chapter
Introduction to the PMP Exam and Project Management Basics
Key term
Training and Development
Training and Development is the process of enhancing team members' skills, knowledge, and competencies to improve project performance and achieve career growth.
Key term
Team Building
Team building is the process of creating a cohesive group of people who work together effectively toward a shared goal.
About these practice questions
One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. An executive stakeholder bypasses the project manager and directly assigns work to a team member. The team member is now overloaded and missing sprint commitments. What should the project manager do first?
hard- A.Escalate to the sponsor about the executive's interference.
- ✓ B.Meet with the executive stakeholder to explain the impact and request that all work requests go through the project manager.
- C.Update the risk register and monitor for further occurrences.
- D.Assign the extra work to another team member to balance the load.
Why B: The correct first step is to discuss the issue with the executive stakeholder privately to reinforce the project governance and communication protocols. This is proactive and respectful. Option A escalates prematurely. Option C ignores the root cause. Option D is reactive and does not address the bypassing behavior.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.