PgMP Program Life Cycle Management Practice Question
You are the program manager. Your program is composed of several projects. One project is finishing early. What is the most important thing you should do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Adjust the program roadmap to reflect the updated schedule and resource availability.
Early completion of a project may impact the program schedule and resource availability; the program manager must adjust the roadmap accordingly.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Immediately close the program.
Why it's wrong here
One project finishing does not mean the program is finished.
- ✓
Adjust the program roadmap to reflect the updated schedule and resource availability.
Why this is correct
The roadmap must remain accurate to the current reality.
- ✗
Allow the project manager to start another project.
Why it's wrong here
This must be done within the scope of the program plan.
- ✗
Decrease the program budget.
Why it's wrong here
Budget changes require formal approval.
About these practice questions
This PgMP question is part of Courseiva's 197-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.