PgMP Program Life Cycle Management Practice Question
You are managing a program and notice that the program-level benefits are not being tracked effectively. What should you update?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Benefits Realization Plan.
The Benefits Realization Plan is the document that specifies how, when, and by whom benefits are tracked and measured.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Program Charter.
Why it's wrong here
The charter is a static document post-approval.
- ✗
The project-level performance reports.
Why it's wrong here
These track outputs, not necessarily final benefits.
- ✗
The Program Management Plan.
Why it's wrong here
This is a high-level document; the specific tracking plan should be updated.
- ✓
The Benefits Realization Plan.
Why this is correct
Updating this plan ensures effective tracking of the program benefits.
About these practice questions
One of 197 original PgMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.