PgMP Program Life Cycle Management Practice Question
When performing program planning, you must ensure alignment with strategic objectives. Which TWO of the following artifacts are critical for ensuring this alignment?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Program Roadmap
The program roadmap and the program business case are essential to map strategic goals to program delivery and justify the ongoing investment.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Component Charter
Why it's wrong here
Project level, not program level.
- ✗
Stakeholder Register
Why it's wrong here
Operational, not strategic alignment.
- ✗
Risk Register
Why it's wrong here
Operational, not strategic alignment.
- ✓
Program Roadmap
Why this is correct
Links objectives to deliverables.
- ✓
Program Business Case
Why this is correct
Provides the economic justification for strategic alignment.
About these practice questions
This PgMP question is part of Courseiva's 197-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.