During a phase-gate review, the Program Manager is asked to present evidence of 'benefit realization' to date. Which metric is most appropriate for a governance board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Realized vs. Planned business benefits

The Board focuses on the realized value that aligns with strategic business objectives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Earned Value Management (EVM) CPI

    Why it's wrong here

    This tracks budget efficiency, not business value realization.

  • Realized vs. Planned business benefits

    Why this is correct

    This directly addresses the strategic purpose of the program.

  • Cumulative project schedule variance

    Why it's wrong here

    This is an operational metric, not a strategic benefit metric.

  • Resource utilization rates

    Why it's wrong here

    This is an administrative/efficiency metric.

About these practice questions

One of 197 original PgMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.