PgMP Program Life Cycle Management Practice Question
A program manager is evaluating a new component project for inclusion in the program. What is the most important factor to consider?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Alignment with the program's strategic objectives and business case.
Strategic alignment is the primary driver for component inclusion in a program.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Alignment with the program's strategic objectives and business case.
Why this is correct
If it does not support the program's purpose, it should not be included.
- ✗
Project budget size.
Why it's wrong here
Size is secondary to strategic value.
- ✗
Availability of project management resources.
Why it's wrong here
Resources can be acquired; strategic fit cannot be forced.
- ✗
Technical complexity of the project.
Why it's wrong here
Complexity is a risk factor, not a selection criterion for alignment.
About these practice questions
One of 197 original PgMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.