PgMP Program Life Cycle Management Practice Question
A program manager discovers that a project manager is not adhering to the program-level quality standards. What should the program manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Discuss the issue with the project manager and request a corrective action plan.
The program manager must address the non-compliance by working with the project manager to identify the issue and implement corrective actions that align with the program's quality management plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Correct the issue themselves.
Why it's wrong here
The project manager needs to be involved in the correction.
- ✗
Immediately replace the project manager.
Why it's wrong here
This is an extreme and reactive measure.
- ✓
Discuss the issue with the project manager and request a corrective action plan.
Why this is correct
This involves the responsible party and ensures accountability.
- ✗
Report the issue to the sponsor.
Why it's wrong here
The program manager should handle this through standard management channels first.
About these practice questions
One of 197 original PgMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.