Your organization shifts its strategy from market growth to cost optimization. How should you adjust the portfolio components?
Trap 1: Wait for the annual budget cycle to propose changes.
Strategic alignment is continuous, not tied to annual cycles.
Trap 2: multiple_choice
...
Trap 3: Continue all projects until completion to avoid sunk costs.
Completion of misaligned projects wastes capital.
- A
Re-evaluate the portfolio inventory against the new strategic objectives.
Strategic alignment requires re-assessing all components whenever organizational strategy changes.
- B
Wait for the annual budget cycle to propose changes.
Why it fails: Strategic alignment is continuous, not tied to annual cycles.
- C
multiple_choice
Why it fails: ...
- D
Continue all projects until completion to avoid sunk costs.
Why it fails: Completion of misaligned projects wastes capital.
- E
Reduce the portfolio budget by 10% across all projects.
Why it fails: Arbitrary cuts don't ensure strategic alignment.