Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Who is responsible for reviewing the End Stage Report and deciding whether to authorize the next stage?

⚠ Common exam trap

PeopleCert often tests the misconception that the Project Manager has the authority to authorize the next stage, but in PRINCE2, the Project Manager only recommends, while the Project Board decides.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

The Project Board is responsible for reviewing the End Stage Report and deciding whether to authorize the next stage. This is a key governance point in PRINCE2, where the Project Board assesses the current stage's performance against the plan and approves moving forward.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The PM produces the End Stage Report but does not authorize the next stage.

  • Executive

    Why it's wrong here

    The Executive is a board member, but decisions are made by the entire Project Board.

  • Senior User

    Why it's wrong here

    The Senior User is part of the Project Board, but authorization is a collective board decision.

  • Project Board

    Why this is correct

    Correct. The Project Board authorizes the next stage.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which process is used by the Project Board to authorize the next stage of a project?

medium
  • A.Managing a Stage Boundary
  • B.Starting Up a Project
  • C.Directing a Project
  • D.Controlling a Stage

Why C: The Project Board authorizes the next stage as part of Directing a Project, based on the End Stage Report and next Stage Plan from SB.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.