Which TWO of the following statements about the Directing a Project process are true?

⚠ Common exam trap

It's easy for candidates to confuse the roles: candidates often think the Project Manager uses Directing a Project for daily tasks, but PRINCE2 clearly assigns that to Managing a Stage, while Directing a Project is the Board's high-level control process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Board uses Directing a Project to authorize the initiation of the project

The Directing a Project process is used by the Project Board to make key decisions and exercise overall control, including authorizing the initiation of the project. The Project Board does not manage day-to-day work; that is the responsibility of the Project Manager via the Managing a Stage process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Project Manager uses Directing a Project to manage day-to-day work

    Why it's wrong here

    The Project Manager does not use Directing a Project for day-to-day work; that is the function of the Managing a Product Delivery and Controlling a Stage processes. Directing a Project is reserved for the Project Board to make key decisions and authorise stage transitions. It is tempting because a manager might assume the process named "Directing" involves hands-on management, but in PRINCE2 it specifically governs high-level oversight, not operational tasks.

  • The Project Board uses Directing a Project to authorize the initiation of the project

    Why this is correct

    Correct: Authorizing initiation is a key decision in DP.

  • The Project Board can give ad-hoc direction during the project

    Why this is correct

    Correct: Ad-hoc direction is part of DP.

  • Directing a Project only occurs at the start of the project

    Why it's wrong here

    DP runs throughout the project for all key decision points.

  • Directing a Project is the process for closing a project

    Why it's wrong here

    Closing is authorized in DP, but the CP process executes the closure.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.