Courseiva

PRINCE2F Business Case and Organizing Practice Question

Which TWO documents are part of the Project Initiation Documentation?

⚠ Common exam trap

PeopleCert often tests the distinction between management products (like the Risk Register and Quality Register) and the core components of the PID, leading candidates to mistakenly include all registers as part of the initiation documentation.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Business Case

In PRINCE2, the Project Initiation Documentation (PID) is the baseline document set assembled during the Initiating a Project process, and the Business Case (option B) is a core component because it justifies the project's continued viability and is included in the PID's 'What is the business justification?' section. The Project Plan (option D) is also part of the PID, since it defines the project's scope, products, activities, resources, and tolerances and forms the baseline against which progress is measured. The Lessons Log (A), Quality Register (C), and Risk Register (E) are project registers/logs that are maintained alongside the project but are not themselves constituent documents of the PID.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Lessons Log

    Why it's wrong here

    The Lessons Log captures lessons from previous or current projects and sits outside the Project Initiation Documentation baseline; it is a separate PRINCE2 record. It is tempting because lessons inform the PID's approach, and would be correct where the question asks which document feeds lessons into project initiation.

  • ✓

    Business Case

    Why this is correct

    The Business Case is part of the Project Initiation Documentation because it provides the justification for undertaking the project, satisfying the PRINCE2 principle of continued business justification. It documents the reasons, options, expected benefits, costs, and risks, forming the basis for the project board’s decision to authorise initiation. Without this, the PID lacks the mandatory business rationale required by the PRINCE2 methodology.

  • ✗

    Quality Register

    Why it's wrong here

    The Quality Register records quality activities and results and is maintained outside the Project Initiation Documentation; the PID contains the Quality Management Approach instead. It is tempting because quality planning is central to initiation, and would be correct where the question asks which register tracks quality checks during delivery.

  • ✓

    Project Plan

    Why this is correct

    The Project Plan is a component of the Project Initiation Documentation, satisfying the requirement that the PID comprises the project plan plus the business case, benefits management approach and other baselined products. It defines the project's scope, products, activities and resource requirements.

  • ✗

    Risk Register

    Why it's wrong here

    The Risk Register is created during Initiating a Project and updated throughout, but it is a separate management product, not a component of the Project Initiation Documentation baseline. It is tempting because the PID references risk tolerances; however, the register itself sits outside the PID's document set.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.