Which THREE of the following are characteristics of a project according to PRINCE2?
Projects involve people from different functions.
Why this answer
Projects are temporary, have a unique output, and involve cross-functional teams. Options A, B, and D are correct. Option C is a characteristic of business as usual.
Option E is false; projects are not permanent.