The Project Manager identifies that the project's approved Business Case is no longer viable. Which process should the Project Manager use to escalate this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Controlling a Stage

The Project Manager should escalate via an Exception Report in Controlling a Stage (CS) or at a stage boundary. However, if within a stage, CS is the appropriate process to raise the exception.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why it's wrong here

    DP is the Board's process.

  • Starting Up a Project

    Why it's wrong here

    SU is pre-project.

  • Closing a Project

    Why it's wrong here

    CP is for closure after the Board's decision.

  • Controlling a Stage

    Why this is correct

    CS includes escalating exceptions via Exception Report.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.