The Project Manager identifies that the project's approved Business Case is no longer viable. Which process should the Project Manager use to escalate this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
The Project Manager should escalate via an Exception Report in Controlling a Stage (CS) or at a stage boundary. However, if within a stage, CS is the appropriate process to raise the exception.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Directing a Project
Why it's wrong here
DP is the Board's process.
- ✗
Starting Up a Project
Why it's wrong here
SU is pre-project.
- ✗
Closing a Project
Why it's wrong here
CP is for closure after the Board's decision.
- ✓
Controlling a Stage
Why this is correct
CS includes escalating exceptions via Exception Report.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.