Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

The Project Board has authorized a Stage Plan. During the stage, the Project Manager identifies a risk that could cause the stage to exceed its time tolerance. What should the Project Manager do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction

According to PRINCE2's management by exception, if a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The PM cannot unilaterally change the plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the Team Manager to accelerate work to stay within tolerance

    Why it's wrong here

    This may be a corrective action, but the PM must first determine if tolerance is threatened; if so, escalation is required.

  • Raise an Exception Report to the Project Board and await their direction

    Why this is correct

    When a stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report to the Project Board.

  • Record the risk in the Risk Register and continue monitoring

    Why it's wrong here

    If the risk is likely to cause a tolerance breach, passive monitoring is insufficient; escalation is needed.

  • Implement a contingency plan to mitigate the risk and continue as planned

    Why it's wrong here

    The PM must first assess if the tolerance will be breached. If yes, escalation is required before implementing changes.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.