PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During which process are the Benefits Management Approach and the Project Plan created?

⚠ Common exam trap

The trap is confusing Initiating a Project with Starting Up a Project; candidates may think the Project Plan is created in Starting Up, but that process only produces the Project Brief, while the detailed plan is created in Initiating.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Initiating a Project

The Benefits Management Approach and the Project Plan are both created during the Initiating a Project process. This process is part of the PRINCE2 methodology where the project's foundation is established, including the business case, project plan, and benefits management approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary reviews the current stage and prepares the next Stage Plan, not the Project Plan or Benefits Management Approach. It tempts because it handles planning documentation, but those two baselines are produced during Initiating a Project.

  • ✗

    Directing a Project

    Why it's wrong here

    Directing a Project covers board-level decisions and continued business justification, not the creation of these products. It is tempting because the Project Board authorises the Project Initiation Documentation, but the Benefits Management Approach and Project Plan are actually produced during Initiating a Project.

  • ✓

    Initiating a Project

    Why this is correct

    Initiating a Project assembles the project's foundations, producing the Project Plan and the Benefits Management Approach alongside the business case and PID. These documents are created here because the process establishes how benefits will be measured and how delivery will be controlled.

  • ✗

    Starting Up a Project

    Why it's wrong here

    Starting Up a Project produces the Project Brief and daily log; the Project Plan and Benefits Management Approach are created in Initiating a Project. It tempts because both are early pre-delivery activities, yet the detailed baselines belong to the initiation process, not the pre-project start-up.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.