During the Controlling a Stage process, the project manager receives a Checkpoint Report from the team manager. What is the primary purpose of this report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To provide the project manager with information on the status of work packages

Checkpoint Reports provide the PM with progress information on work packages, including actuals, forecasts, and issues, to support day-to-day management.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To provide the project manager with information on the status of work packages

    Why this is correct

    Correct. Checkpoint Reports are from TM to PM about work package status.

  • To request changes to the work package

    Why it's wrong here

    Changes are managed via the issue and change control process.

  • To inform the project board of the stage's overall progress

    Why it's wrong here

    That's the purpose of the Highlight Report, not Checkpoint Report.

  • To escalate any issues that cannot be resolved by the team manager

    Why it's wrong here

    Issues are escalated via issue reports or other means; Checkpoint Reports are for status.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from a Team Manager. What is the primary purpose of this report?

hard
  • A.To inform the Project Board of stage progress
  • B.To request changes to the Project Plan
  • C.To escalate issues to the Project Board
  • D.To provide details of Work Package progress to the Project Manager

Why D: Checkpoint Reports are produced by Team Managers to inform the PM of progress on Work Packages.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.