A Project Manager is about to begin work on a new stage. Which document provides the authority to proceed with the stage?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stage Plan

The Project Board authorises the stage by approving the Stage Plan. Work cannot start without this authorised plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Brief

    Why it's wrong here

    The Project Brief is created in SU and used for initiation, not stage authorisation.

  • Stage Plan

    Why this is correct

    The approved Stage Plan gives the PM authority to execute the stage.

  • Project Initiation Documentation

    Why it's wrong here

    PID is the overall project baseline, not stage-specific authority.

  • Business Case

    Why it's wrong here

    The Business Case justifies the project but does not authorise stages.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.